Fruitport Rd Construction Update
Repaving of N. Fruitport Rd. is continuing and is scheduled to be finished on Friday, August 7. The anticipated schedule is:
7/23 - Milling and some paving 7/24 - Manhole adjustments 7/30 and 8/1 - Second coat of asphalt for the entire road 8/2 - Not working 8/3 - Pave driveways 8/4 and 8/5 - Gravel shoulders 8/6 - Paint lines on the road 8/7 - Finish
We can now see how great Fruitport Road will look for a long time! Thanks to everyone for their patience as this necessary work was completed.
|