Fruitport Rd Construction Update

construction cone
Repaving of N. Fruitport Rd. is continuing and is scheduled to be finished on Friday, August 7. The anticipated schedule is:

7/23 - Milling and some paving
7/24 - Manhole adjustments
7/30 and 8/1 - Second coat of asphalt for the entire road
8/2 - Not working
8/3 - Pave driveways
8/4 and 8/5 - Gravel shoulders
8/6 - Paint lines on the road
8/7 - Finish

We can now see how great Fruitport Road will look for a long time! Thanks to everyone for their patience as this necessary work was completed.