Wadsworth -131 Construction Update

 

Construction improvements continue along Wadsworth Road and Green Bay Road.  The following is the anticipated schedule of construction activities for the next few weeks. (Weather Permitting)

 


 

Remaining this Week (9/16):

  • Storm sewer installations and fire hydrant relocations continue, followed by the preparation for the temporary pavement;
  • Fine grading will be completed for the temporary pavement on the south leg of Green Bay Road when the weather allows;

 

Week of 9/23:

  • The fire hydrant relocations should be completed;
  • Temporary pavement will be placed on Green Bay (south);
  • Excavation and preparation for the temporary pavement on Wadsworth Road (west of Green Bay) will begin;
  • Removal of curb and gutter and pavement will begin on the east leg of Wadsworth Road;

 

Looking ahead to the Week of 9/30:

  • Excavation and preparation for the temporary pavement on the east leg of Wadsworth Road will continue;
  • Temporary pavement will be placed on the west leg of Wadsworth Road and the north leg of Green Bay Road;

  

 

If you have any comments or concerns, please contact me at: dhewitt@lakecountyil.gov or 847.244.2742.

 