Construction improvements continue along Wadsworth Road and Green Bay Road. The following is the anticipated schedule of construction activities for the next few weeks. (Weather Permitting)
Remaining this Week (9/16): - Storm sewer installations and fire hydrant relocations continue, followed by the preparation for the temporary pavement;
- Fine grading will be completed for the temporary pavement on the south leg of Green Bay Road when the weather allows;
Week of 9/23: - The fire hydrant relocations should be completed;
- Temporary pavement will be placed on Green Bay (south);
- Excavation and preparation for the temporary pavement on Wadsworth Road (west of Green Bay) will begin;
- Removal of curb and gutter and pavement will begin on the east leg of Wadsworth Road;
Looking ahead to the Week of 9/30: - Excavation and preparation for the temporary pavement on the east leg of Wadsworth Road will continue;
- Temporary pavement will be placed on the west leg of Wadsworth Road and the north leg of Green Bay Road;
|
|