Use Rammed Aggregate Pier� (RAP) Elements to Replace Piles or Drilled shafts

 

 

 

Spread Footings, Intermediate Foundations or Deep Foundations

Prior to the introduction of Geopier Intermediate Foundation Systems, geotechnical engineers had two choices when it came to foundations types, either the soils were good enough to support spread footings or a deep foundation system such as piles or drilled shafts were needed. There were no intermediate options.

 

 

 


 

 

When should you choose Geopier ground improvement over deep foundations?

 

Ground improvement is typically less expensive than piles or drilled shafts when one of the following is true: 

  • Piles and drilled shafts are 25 feet long or greater
  • Pile allowable axial capacity is 150 kips or less
  • Drilled shaft allowable end-bearing pressure is 60 kips per square foot (ksf) or less

 

Ground improvement technology has improved over the last 20 years and geotechnical engineers have embraced the use of ground improvement or Intermediate Foundation Systems, where marginal soils can be improved in place to control settlement of spread footing foundations.  As a result of continuous innovations, some of the advantages of Geopier Rammed Aggregate Pier elements (RAP) and Geopier rigid inclusions (discussed in the 2014 July, August and September Newsletters) are:

 

  • Ability to Install ground improvement  to depths up to 65 feet
  • Geopier rigid inclusion capacities of 75 to 250 kips can be obtained
  • Installation can take place above or below the groundwater table
  • Displacement methods such as Geopier Impact� Pier System can be used to minimize/eliminate contaminated spoils
  • Grout and/or concrete can be used in RAP elements to span soft or organic zones in a soil profile

 

With these improvements in Geopier Technology, the applications for ground improvement have expanded.

 

 

Pile Replacement Example

 

Geopier rigid inclusions replaced a pile foundation on the Station 650 (Land Bay J) multi-family project in Alexandria, VA.  The soil conditions consisted of approximate 10 feet of contaminated urban debris fill overlying 8 feet of soft clay, 35 feet of loose to dense sands, underlain by very stiff Potomac Group clays. The original geotechnical report recommended 80-ton 14x73 steel H-Piles or 80-ton,  14-inch square-precast concrete piles driven 65 feet into very stiff Potomac Group clay.  The piles were replaced by 50-foot deep grouted Impact Pier elements (Geopier rigid inclusions).  The Geopier rigid inclusions tested for the project deflected 0.04 inches at a load of 50 tons.  

 

 

 

 

By using Geopier ground improvement in lieu of piles on the Station 650 Project the owner was able to:

  1. Take advantage of a faster installation schedule, which meant they could move in their first tenant earlier, and
  2. Support the building on an engineered system that cost less money.  Some of the specific cost savings included:
    • Use of spread footings vs. pile caps which meant less concrete
    • Eliminated pile cutoffs which resulted in a quicker installation
    • Geopier installation saved time on the construction schedule over piles 

 

 

Drilled Shaft Replacement Example

 

Geopier rigid inclusions were used on the Towson University Liberal Arts Building - Phase II in Towson, MD to replace a drilled shaft foundation system. The building was sited such that footings for the western section of the building could bear on decomposed rock with an allowable bearing pressure of 7.5 ksf, but fill soils and loose residual silty sands required a deep foundation system in the eastern section. The soil conditions for the eastern section consisted of approximate 10 feet of loose silty sand fill, overlying 25 feet of natural, loose to dense residual silty sands, which were underlain by decomposed rock and highly weathered to weathered gneiss bedrock. The original geotechnical report recommended that all shafts be a minimum of 36 inches in diameter, so that the bottom could be inspected to verify shafts were bearing on suitable material.  Due to the variability of the weathering in the bedrock profile, drilled shafts needed to be socketed into rock with an RQD (Rock Quality Designation) of at least 50%.  The shafts were designed for an allowable bearing pressure of 40 ksf.   

 

 

The general contractor, who was familiar with Geopier RAP elements, proposed an alternate of 30-inch diameter RAP elements.  The RAP elements supported spread footings designed for 6 ksf bearing and controlled settlement to less than 1 inch.  Having a designed system that was consistent with the spread footings used on the western section of the building simplified the design and construction sequencing for the GC and the owner. 

 

The Geopier alternative proved to be faster and eliminated the risk of potential overruns associated with variable drilled shaft lengths, rock socket depths, and rock testing to find rock with an RQD > 50%.  

 

Using ground improvement versus drilled shafts on the Towson Project provided the owner the assurance that the foundation would be completed on schedule with no cost overruns.  Specific benefits included:

 

  • Ability to use spread footings for all the foundations
  • Eliminating the requirement to socket piers into rock or case holes for inspection and testing
  • Eliminating the risk of overruns due to encountering poor quality rock
  • Generating fewer spoils saving time and haul-off costs


Bottom Line
 

 

  • Intermediate Foundations are your next best choice to natural soils.
  • Owners and Contractors do not want to spend more money than necessary on the foundation system for any structure. 
  • When fill soils or compressible natural soils and/or very high structural loads result in excessive unacceptable settlements your next choice is Geopier ground improvement.
  • With a wide range of Geopier ground improvement tools available, a customized solution can be developed to solve most every foundation challenge.

 

 
Grounded Solutions March newsletter will discuss the use of Ground Improvement for floor slab and mat foundation support.

 

                           

                     

If you have a project that could benefit from the use of Geopier ground improvement visit our website to submit a Project Assessment.

OR CALL:  703-771-9844

Interested in scheduling a site visit?
Send us an email

 

 



News & Events

10th Annual Technical Conference (March 3rd)
Charlotte, NC
The conference is an opportunity to learn more about earth and foundation support technologies. Join us to see how you can save your clients time and money.  For more information and registration visit our website.


10th Annual Technical Conference (March 12th)
New York, NY
The conference is an opportunity to learn more about earth and foundation support technologies. Join us to see how you can save your clients time and money.  For more information and registration visit our website.


National Engineers Week
(February 28th)
Washington, DC
National Building Museum
Discover Engineering Family Day is a fun-filled day designed to introduce students 4 to 12 to the wonder of engineering and the importance of technological literacy. It attracts thousands of people and wraps up Discover Engineers Week activities in the national capital area. For more information visit:



Featured Projects

In Progress

The Majestic at Watkins Mill
Gaithersburg, MD
Geopier elements are being installed to support the construction of the new 243-unit multi-family apartment development which will include three outdoor terraces and a plethora of indoor amenity space overlooking Performers Park.  To learn more or schedule a site visit send us an email.


Completed

Ambler Savings Bank
Ambler, PA
Impact Pier elements were installed for foundation support of the new building designed to provide the highest caliber of modern banking services.  Project details available here.  





In honor of National Engineers Week!