Five lanes now open on Hulen Street bridge
A third northbound lane and a second southbound lane opened on the Hulen Street bridge in Fort Worth last week, providing motorists with five total traffic lanes. The lanes were opened March 27, after crews completed median work along the new bridge.
In the next few weeks, the northbound lanes will be reduced to two lanes temporarily so crews can install fencing. By the end of summer, the entire bridge will open, giving motorists six traffic lanes, three in each direction and pedestrians a 10-foot sidewalk on the northbound side of the bridge.
Work continues at I-20/SH 183 interchange in south Fort Worth
At the Interstate 20/State Highway 183/CTP interchange, crews are busy pouring columns and building bridge decks. The following closures are scheduled:
*April 3-18: The closure of the westbound I-20 exit ramp to Bryant Irvin Road
*April 3-Late June: Nightly closure of two eastbound I-20 lanes
Progress continues on Oakmont Boulevard bridge
The westbound bridge deck of the Oakmont Boulevard bridge over the CTP main lanes was constructed last week, completing the two parallel bridges. Crews continue working on approaches, railing and other final details as they complete the structures and prepare for an opening date late this spring.