Upper Kirby District Street Talk
Join Our Mailing List
In This Issue:
Westheimer Construction
US 59 Feeder Construction
Upper Kirby Streetscape Initiatives

Before


Join Our Mailing List
After
Coming to a Major Thoroughfare Near You!!!
Community Resources:


Upper Kirby Update

January 16, 2015
Upper Kirby Construction
Construction to Begin on Westheimer: Kirby to Shepherd

  

Westheimer Reconstruction: Kirby to Shepherd

Over the past several months work on the drainage, pavement and streetscape improvements project on Westheimer between Kirby and Shepherd has focused on the installation of a large four-by-six-foot storm sewer box on Dickey Place between Westheimer and Reba. As the final piece of work on Dickey between Westheimer and San Saba begins preparations for pavement placement, crews are now eying the primary storm sewer installation on the north side of Westheimer between Kirby and Shepherd.

 

The original plan was to take possession of the intersection of Shepherd and Westheimer on January 5th and begin work from Shepherd west to Persa, however, the City of Houston project on Shepherd between Westheimer and Buffalo Bayou is still working in the intersection and east of the intersection, preventing Upper Kirby work from beginning as planned.  

 

In an effort to not halt work altogether, Upper Kirby and Reytec are planning to begin installing storm sewer moving west from the outfall point at Dickey as early as Monday. This will allow the City contractor time to complete his work at Shepherd while still making meaningful progress toward the completion of Westheimer.  

 

In order to regain time lost due to this re-sequencing, Upper Kirby is pursuing approval to bring in additional crews to work concurrently moving east from Dickey toward Persa. If approved, this extended work zone could shave significant time off of the potential impacts of the City work being in the Shepherd/Westheimer intersection much longer than anticipated. Once the City contractor has vacated the intersection, Reytec has committed the resources necessary to move into the intersection quickly to complete final reconstruction.

 

During this first phase of work on Westheimer, motorists should expect to be transitioned down to one lane in either direction on the south side of the street. Once work on the northernmost lanes is complete, traffic will flip for work to begin on the south side of Westheimer. Expect this situation between Kirby and Dickey next week, however, if approved, this configuration could extend from Kirby roughly to Persa. Look for further updates as plans are finalized.



Bissonnet Utility Relocation
Existing Pedestrian Realm on Bissonnet

Bissonnet Utility Relocation from Kirby to Buffalo Speedway is nearing completion. Crews are working to restore the pavement along Bissonnet between Wakeforest and Buffalo Speedway, but have completed all duct installation along that route.

Crews have also completed the manhole work just east of the Kirby intersection and will be restoring that pavement today and tomorrow. There is one remaining run of duct work to take place on Wakeforest north of the intersection over the weekend and one run along Dincans. It is anticipated that all remaining work within the main lanes will be completed by mid week next week.

Crews still have several runs of duct behind the curb and will be out over the next few weeks to restore the back of curb areas, but for the most part, construction should be substantially complete next week.

At that time, Upper Kirby will turn over the underground duct banks to the Center Point and the telecommunications providers on the street for final relocation and pole removal. Once Center Point Energy and the telecommunications providers have switched service from overhead to underground and removed the wires and wooden poles, Upper Kirby will begin water, sanitary and storm improvements and roadway reconstruction.

Like Kirby, Buffalo Speedway and Westheimer, this project will include a complete pedestrian-oriented streetscape and landscaping plan implemented and maintained in perpetuity by the Upper Kirby Management District. The roadway is not being widened and the existing esplanade is being maintained.

Like was the case on Westheimer, once underground facilities are in place they will be turned over to the utility companies to transfer overhead service to underground. The roadway reconstruction can begin once the utility companies have completed their work (typically around three months from completion of the duct installation). Once roadway work has begun, it will take 10 to 12 months to complete the project.

Look for further updates as the schedule progresses.

 

For more information on Upper Kirby construction and related activities or for construction related issues or concerns, please contact Travis Younkin at 713.524.8000 or travis@upperkirby.org.   

Chevron Houston Marathon
Sunday, January 18

   

The 2015 Chevron Houston Marathon and Aramco Houston Half Marathon will be held on Sunday, January 18, 2015 and will take runners on a course that winds throughout the City and bisects the Upper Kirby District.

Spectators can watch the excitement at the starting line located at Congress and San Jacinto, along the route on Congress (outbound), Lamar (inbound) or at the finish line which will be located in front of Discovery Green. Upper Kirby spectators can join businesses and sponsors at a number of stations along Kirby Drive from Westheimer to Bissonnet.

Be sure to check out the 2015 We Are Houston RunFest on the Jones Lawn at Discovery Green following each race, where a festive atmosphere will make for a great place to meet up with friends and family. And don't miss the Memorial Hermann Ironman Sports Medicine Institute Expo on Friday, January 16 and Saturday, January 17, where vendors from around the country will be at the GRBCC with the latest in running gear, health and fitness products, clothing and more.

Don't forget that with the marathon comes street closures. View the full route here for a complete list of street closures.

For more information on this weekend's festivities, click here.  

If you have a new business, development or community event that you would like included in the monthly Upper Kirby news, please contact us at 713.524.8000 or submit to streettalk@upperkirby.org
 
Requests will be posted subject to space availability and appropriateness of content.
Upper Kirby is a constantly evolving urban area marked by an outstanding location, great shopping, unique residential neighborhoods, smart development and a small town feel. It is an area of successful businesses, involved communities and a synergy between the public and private sectors. It is the heartbeat of Houston and everywhere you want to be.