Upper Kirby District Street Talk
Join Our Mailing List
In This Issue:
US 59 Feeder Construction
Westheimer Construction
Upper Kirby Streetscape Initiatives

Before


Join Our Mailing List
After
Coming to a Major Thoroughfare Near You!!!
Community Resources:
Welcome to the new Levy Park
Construction to begin this fall.
Look for weekly updates soon.

Upper Kirby Update

  October 24, 2014  
TxDOT Construction - US 59
Buffalo Closed at US 59 for Several Weeks     
 

   

US 59 Frontage Road Reconstruction

TxDOT's US 59 frontage road reconstruction between Shepherd and 610 continued this week with intersection work at Greenbriar, Shepherd and Buffalo Speedway.

The Buffalo Speedway intersection construction began on main lanes under US 59 on Wednesday morning.
TxDOT has given the contractor full access to all through lanes allowing them to expedite the reconstruction at the expense of detouring all Buffalo Speedway traffic along the frontage road to the next available u-turn. The contractor has been given 30 days to complete this work though TxDOT has offered an early completion incentive for up to seven days. Motorists should consider Weslayan, Edloe, Westpark, and Richmond as alternate routes to negotiate around the Buffalo/59 intersection during peak hours.

The Shepherd intersection and underpass pavement reconstruction is a bit further along. Main lanes under the freeway on Shepherd are complete and quadrant work is underway. This work is expected to be completed by the end of October with the Greenbriar/Shepherd exit inbound being ready to reopen to traffic around October 31.

Work at Greenbriar is also ongoing though completion here will lag slightly behind. Motorists should expect one lane through these intersections while the quadrants are being reconstructed.

Look for weekly updates as this project progresses.   

 

For a regularly updated list of lane closures and on and off-ramp closures, visit Houston Transtar here.    

Upper Kirby Construction
Curbside-Lane Work on Kirby Southbound Postponed - Telecom Install Continues      

  

Bissonnet Utility Relocation
Existing Pedestrian Realm on Bissonnet


Bissonnet Utility Relocation from Kirby to Buffalo continued this week with efforts toward the construction of parallel ducts along the north side of Bissonnet, one for telecommunications and one for Center Point electrical service. 

Work is expected to continue next week with telecommunications duct installation as well as bore/tunneling work at the Kirby intersection. It was thought that trench work in the curbside lane southbound on Kirby would begin this week, but the contractor has postponed this work in light of the increased demand on Kirby traffic stemming from TxDOT work at 59 currently impacting Buffalo Speedway. While there will likely still be some overlap, this work will likely not begin for two to three weeks. 

The contractor has also indicated that he will be ready to begin utility duct installation through the north side of the Wakeforest intersection in approximately two weeks. When this work begins Wakeforest will be closed onto and off of Bissonnet from the south. Northbound movements on Wakeforest will be maintained.

The ducts installed during this phase of work will eventually house the overhead
Utility Work - Bissonnet at Kirby
lines currently running down Bissonnet. Once Center Point Energy and the telecommunications providers have switched service from overhead to underground and removed the wires and wooden poles, Upper Kirby will begin water, sanitary and storm improvements and roadway reconstruction. Like Kirby, Buffalo Speedway and Westheimer, this project will include a complete pedestrian-oriented streetscape and landscaping plan implemented and maintained in perpetuity by the Upper Kirby Management District. The roadway is not being widened and the existing esplanade is being maintained.

The utility phase of this project was bid in August and was awarded to Harper Brothers Construction. It is anticipated that, weather permitting, this work will take four to five months to complete. Like was the case on Westheimer, once underground facilities are in place they will be turned over to the utility companies to transfer overhead service to underground. The roadway reconstruction can begin once the utility companies have completed their work (typically around three months from completion of the duct installation). Once roadway work has begun, it will take 10 to 12 months to complete the project.

Look for further updates as the schedule progresses.

 

Concrete Framing at Dickey Place

 

Westheimer Drainage, Paving and Streetscape Improvements: 

Shepherd to Kirby

Reytec Construction has completed work at the Reba/Dickey intersection north of Westheimer in the first phase of drainage improvements that will take storm water from Westheimer into the Shepherd system. The Reba/Dickey interchange has been reopened and installation of the box culvert between Reba and Locke has been completed. Crews should be ready to begin concrete work between Reba and Locke next week. The plan from there will be to push storm sewer installation through the Locke intersection and continue through to San Saba. The Locke/Dickey intersection will be restored temporarily and crews will come back for new concrete work at the intersection later in the process.

During the Dickey work, crews will continue progressing from Reba south to Westheimer installing a 4-foot by 6-foot storm drain to replace the 42-inch drain currently running under private properties just west of Dickey. 
 
No two intersections will be impacted at one time. Neighborhood traffic will be detoured around work areas during this phase. This work will include new inlets at intersections and complete concrete restoration of the roadway. Driveways will be impacted as work moves down the street and will be restored with new concrete within the City right-of-way. 

The Upper Kirby District is coordinating this work with the City of Houston drainage and pavement reconstruction on Shepherd between Westheimer and Buffalo Bayou. The City is currently working north of the Shepherd/Westheimer intersection, however, the contractor has erected traffic control through the full length of the project from Westheimer to Buffalo Bayou. Reytec hopes to begin work at the Shepherd/Westheimer intersection in January, however, their ability to do so will henge on the City contractor being done in the intersection and shifting their traffic control north.

City contractors will be working 24 hours a day, seven days a week on this section. They will install drainage improvements, water and sanitary as needed moving south from Avalon to Westheimer and East along Westheimer for about two blocks. Motorists should expect to be down to one lane in either direction to pass through the construction area. The City has committed to clear the intersection as quickly as possible and restore traffic along Westheimer, though work here has not yet commenced.

While the City is working in the intersection, Upper Kirby will remain clear of Westheimer and will focus on the primary outfall point for storm water along this section at Dickey Place. Should a situation occur where The City has not vacated their work along Westheimer, Reytec may look to begin at the other storm sewer outfall point at Dickey and Westheimer and work west toward Kirby in an effort to maintain the construction schedule. Look for further updates as these two projects progress.

Once work on Dickey is complete, crews will demobilize for the time between Thanksgiving and January 2 in hopes that the City has also completed work through the Shepherd/Westheimer intersection and has opened Westheimer to unobstructed traffic flow for the holidays. City work will continue over the holidays north of the intersection but will observe Thanksgiving and the day after, Christmas Eve, Christmas Day, New Year's Eve and New Year's Day.

For more information on Upper Kirby construction and related activities or for construction related issues or concerns, please contact Travis Younkin at 713.524.8000 or travis@upperkirby.org.   

If you have a new business, development or community event that you would like included in the monthly Upper Kirby news, please contact us at 713.524.8000 or submit to streettalk@upperkirby.org
 
Requests will be posted subject to space availability and appropriateness of content.
Upper Kirby is a constantly evolving urban area marked by an outstanding location, great shopping, unique residential neighborhoods, smart development and a small town feel. It is an area of successful businesses, involved communities and a synergy between the public and private sectors. It is the heartbeat of Houston and everywhere you want to be.