Westheimer
Paving, Drainage and Streetscape Improvements Project:
Work continued this week on the second and third phases of work along Westheimer between Kirby and Buffalo Speedway.
Workers continue to push east from Eastside with both telecommunications and electric duct bank installation. Traffic begins to taper down to one lane eastbound around River Oaks Boulevard to get around the construction at Eastside. At this point, it appears that the contractor will be ready to move substantially to work between Ferndale and Lake and should be able to open up traffic from River Oaks Boulevard to Bammel on Monday.
Next week work will focus on bore pit excavation at several locations in preparation for telecommunications installation as well as open trench digging for the electric duct bank all the way to Lake Street.
As was the case east of Kirby, construction will be undertaken in 1000-foot segments. Work on this stretch will impact the two eastbound lanes on the south side of Westheimer. Traffic will be shifted to one lane in either direction through the construction zone. Each 1000-foot segment is expected to take four to five weeks to complete. Once a given segment is completed, it will be restored with asphalt and opened prior to the next segment beginning.
The contract duration on this project is 120 days putting completion somewhere around June/July 2014. Weather permitting, roadway construction between Kirby and Shepherd should be able to begin immediately following utility completion west of Kirby.
CenterPoint and the telecommunications companies will follow behind duct bank construction reconnecting services underground. The duration of this reconnection work will be up to the utility providers though 45 to 90 days is typical. Traffic impact during this work is negligible. Once the utilities have been removed and the lines brought underground west of Kirby, Upper Kirby will move forward with drainage and underground infrastructure improvements followed by complete repaving of the roadway. The project will also entail the installation of a pedestrian-oriented streetscape similar to the treatment provided on the recent Kirby Drive and Buffalo Speedway projects. This work will first be completed between Shepherd and Kirby followed by an identical scope of work between Kirby and Buffalo Speedway. Roadway reconstruction is anticipated to last approximately 10 months. Drainage improvement and roadway reconstruction between Kirby and Buffalo will immediately follow and will have a similar approximate duration. For more information on Upper Kirby construction and related activities or for construction related issues or concerns, please contact Travis Younkin at 713.524.8000 or travis@upperkirby.org. |