Upper Kirby District Street Talk
banner
In This Issue:
Westheimer Construction
US 59 TxDot Construction
San Felipe Bridge Closure Sept. 22
Surls on Kirby:
Coming Soon

Community Resources
Graffiti Problem?
Click here to contact us about graffiti abatement services.
 
graffiti

Clogged Inlets? Click here  to Request Area Inlet Maintenance 
inlet clean up

 
UK Phone Booth
Upper Kirby District
Join Our Mailing List

Upper Kirby Update 

September 13, 2013  

Upper Kirby Construction
Project Moves East
Duct Bank Installation on Westheimer

 

Westheimer  

Paving, Drainage and  Streetscape Improvements Project: 

 

Utility duct bank construction on Westheimer between Shepherd and Kirby has moved to the next 1000-foot section of work just east of Dickey Place. Crews are expected to continue with the installation of two parallel duct banks in this section for the next three to four weeks. Work will then move to Shepherd for a similar duration. The final phase of utility work will take place on the south side of the roadway between Kirby and Argonne in preparation for the continuation of underground duct work on the south side of Westheimer all the way to Buffalo Speedway.

Once the underground duct banks are constructed, the roadway will be temporarily paved and striped allowing full vehicular access while CenterPoint and the telecommunications companies reconnect services underground. The duration of this reconnection work will be up to the utility providers though 45 to 90 days is typical.

 

While the various utility companies work to reconnect the eastern half of Westheimer, the Upper Kirby Redevelopment Authority (UKRA) will aim to begin duct bank construction between Kirby and Buffalo Speedway. The UKRA expects to bid this western section of Westheimer later this summer.   

 

Once the utilities have been removed and the lines brought underground east of Kirby, Upper Kirby will move forward with drainage and underground infrastructure improvements followed by complete repaving of the roadway. The project will also entail the installation of a pedestrian-oriented streetscape similar to the treatment provided on the recent Kirby Drive and Buffalo Speedway projects. Roadway reconstruction is anticipated to begin early in 2014 and last approximately 10 months.

 

For more information on Upper Kirby construction and related activities or for construction related issues or concerns, please contact Travis Younkin at 713.524.8000 or travis@upperkirby.org.   

TxDOT Frontage Road Work
Work Continues Between Kirby and Weslayan.

 

US 59 Frontage Road Reconstruction

 

TxDOT has demolished the curb-side lane of the US 59 service road between Kirby and Buffalo and has already begun laying asphalt sub-base and framing for concrete. This section of frontage road is the next in a pavement replacement project that will run from 610 at US 59 all the way to Shepherd. Work is expected to continue here through late November.

   

During off peak hours, motorists should expect only  one lane of traffic to be available  around the construction zones. Morning and afternoon commutes should see multiple lanes available to traffic. Motorists with destinations on the south side of US 59 should consider Westpark as an alternative route as most properties along this frontage road are also accessible from Westpark driveways.

Look for a more detailed update and schedule next week.
Harris County Flood Control Work
San Felipe Bridge Closure Two Weeks Out
null
San Felipe Map of Alternate Routes

The following notice is from the Harris County Flood Control District (HCFCD):

In approximately two weeks, or on September 22, 2013, the Harris County Flood Control District will close the San Felipe Street bridge located at the railroad tracks just east of Mid Lane inside West Loop 610 in the Galleria area.  

 

The bridge will be closed to all traffic for up to two weeks while the 50-year-old bridge is demolished and replaced.  Crews will be working extended hours to expedite completion and minimize inconvenience. Please note: Road closures and construction schedules are subject to change. The Flood Control District will notify the public if there are modifications to this schedule. 

 

If their ultimate destination is not in the area, motorists are encouraged to avoid the area while the bridge is under construction and to use an alternate route. Possible alternate routes include West Loop 610, Memorial Drive, Westheimer Road, Richmond Avenue or Kirby Drive. Signs announcing the street closure dates will be installed in the area prior to the closure. Motorists are encouraged to be alert, to pay attention to all posted street and lane closures and to take an alternate route. The San Felipe bridge closure schedule is subject to change due to construction or weather issues.

 

The Flood Control District appreciates the community's patience during the bridge closure project and regrets any inconvenience caused to residents, business owners and motorists in the area.  

 

The San Felipe bridge replacement is part of the Flood Control District's $13.2 million W129-00-00 Channel Enclosure Project, which is rebuilding and enclosing the poorly functioning drainage channel formally identified as HCFCD Unit W129-00-00. The work spans the section of W129-00-00 from San Felipe to Richmond and includes enclosing the drainage channel with dual 12-foot by 10-foot reinforced concrete box culverts and replacing the bridges at Westheimer and San Felipe. The Westheimer bridge replacement was completed in April 2013. The City of Houston is contributing funds to the bridge projects.

 

For more information about the project, visit the W129-00-00 Channel Enclosure Project webpage at www.hcfcd.org/W129. If you have questions or comments, please call the Flood Control District's Project and Study Information Line, which is monitored daily, at 713-684-4040.


If you have a new business, development or community event that you would like included in the monthly Upper Kirby news, please contact us at 713.524.8000 or submit to streettalk@upperkirby.org
 
Requests will be posted subject to space availability and appropriateness of content.
Upper Kirby is a constantly evolving urban area marked by an outstanding location, great shopping, unique residential neighborhoods, smart development and a small town feel. It is an area of successful businesses, involved communities and a synergy between the public and private sectors. It is the heartbeat of Houston and everywhere you want to be.