Upper Kirby District Street Talk
banner
In This Issue:
Harris County Flood Control Project Update
Construction Update
Community Resources
Graffiti Problem?
Click here to contact us about graffiti abatement services.
 
graffiti

Clogged Inlets? Click here  to Request Area Inlet Maintenance 
inlet clean up

 
UK Phone Booth
Upper Kirby District
Join Our Mailing List

Upper Kirby Update 

March 1, 2013  

Update:
Harris County Flood Control
Chanel Enclosure Project

Westheimer Closure Alternate Routes
Westheimer Bridge Closure- Alternate Routes

 

From the Harris County Flood Control District:

 

Due to construction delays, the Harris County Flood Control  

District has postponed the March 3 closure of two lanes of the Westheimer Road Bridge located just east of Mid Lane inside  West Loop 610 in the Galleria area. The lane closure is now scheduled to start on March 10 and traffic will be limited to one lane in each direction for up to a month while the 50-year-old bridge is demolished and replaced. This schedule is subject to change due to construction or weather issues.

 

The Westheimer bridge replacement project is part of the Flood Control District's $13.2 million W129-00-00 Channel Enclosure Project, which is rebuilding and enclosing the poorly functioning drainage channel formally identified as HCFCD Unit W129-00-00. The work spans W129-00-00 from San Felipe to Richmond and includes enclosing the drainage channel with dual 12-foot by 10-foot reinforced concrete box culverts and replacing the bridges at Westheimer and San Felipe. The City of Houston is contributing funds to the bridge projects.

 

If their ultimate destination is not in the area, motorists are encouraged to avoid the area while the bridge is under  

construction or to use an alternate route. Possible alternate  

routes include West Loop 610, Memorial Drive, San Felipe  

Street, Richmond Avenue or Kirby Drive. Signs announcing the lane closure dates have been installed in the area. Motorists are encouraged to be alert, to pay attention to all posted street and lane closures and to take an alternate route.

 

For more information about the project, visit the W129-00-00 Channel Enclosure Project webpage at  www.hcfcd.org/W129.

If you have questions or comments, please call the Flood Control District's Project and Study Information Line, which is monitored daily, at 713-684-4040. 

Richmond Drainage Improvements:  
Substantial Completion Ahead

Richmond  

Construction 

Crews were out on Richmond today putting the permanent lane striping down. This is the final significant activity on this project. Next week, Upper Kirby's project management team will walking the job and assembling a final punch list of items to be completed by the contractor. Items on this list typically involve restoration or minor back-of-curb adjustments to be completed before the project is accepted. 

The Upper Kirby District would like to thank the businesses and property owners along Richmond for their patience
and understanding. We would also like to thank the patrons who suffered the inconveniences that come with this level of roadwork to support these great local businesses during construction.
 

Westheimer Drainage Improvements and Streetscape Installation 

 

Design is now nearly complete on the Westheimer Paving, Drainage and Streetscape Improvements Project between Shepherd and Buffalo Speedway. This is the final piece of storm drainage work needed to complete the Kirby system.

Work on Westheimer will follow the scope of the Kirby Drive reconstruction project fairly closely. It will entail the burial of all overhead utility lines; new storm drainage, water and sanitary facilities; complete roadway repaving and the installation of a full pedestrian-oriented streetscape that will include pedestrian lighting and furniture, street tree installation and irrigation, brick paved crosswalks, widened sidewalks and upgraded traffic signal and streetlight standards.

The project will be implemented in two sections, the eastern phase will extend from Shepherd to Kirby Drive and the western phase will continue from Kirby to Buffalo Speedway. Each of these phases will be split into a utility relocation phase followed by a roadway, infrastructure and streetscape phase.

The project will likely begin at Shepherd where the contractor will be responsible for constructing the underground duct-banks that will house the existing overhead wires in the future. The contractor will then asphalt over the work area, re-stripe the roadway and remove all traffic control and equipment.

We will close out the contract at this point to avoid disruption to the traveling public and to the local businesses and property owners while we wait for Center Point and all telecommunication companies to transfer services to the new underground facilities and remove the wooden utility poles. Because the length of this process is uncertain, we have planned the project to pause and restore the roadway completely while the utility companies are completing their work. Once the terminal poles have been removed by Center Point, we will bid the roadway phase of the project and begin the reconstruction.

The first utility phase, originally planned to bid in December will wait to bid likely until late March. The design has met with some delay in the city review and comment phase but should be signed and ready to advertise by the end of the month. Please look for further detail on the timing and implementation of this project as plans are finalized.  

 

For more information on Upper Kirby construction projects and for issues and concerns as construction progresses, contact Travis Younkin at 713.524.8000 or email travis@upperkirby.org.        

If you have a new business, development or community event that you would like included in the monthly Upper Kirby news, please contact us at 713.524.8000 or submit to streettalk@upperkirby.org
 
Requests will be posted subject to space availability and appropriateness of content.
Upper Kirby is a constantly evolving urban area marked by an outstanding location, great shopping, unique residential neighborhoods, smart development and a small town feel. It is an area of successful businesses, involved communities and a synergy between the public and private sectors. It is the heartbeat of Houston and everywhere you want to be.