DEVELOPMENT UPDATE
Despite the wet weather and public holidays in April and May progress is still going well. All in-ground services are complete with the majority of kerb and guttering also complete. Gravel sub-base to roads is underway with footpath and driveways commencing shortly.
Council has commenced the process for the construction of a new sewage system for the village and plans are also underway for a new water supply pipeline from Yass to supplement the village water supply. Both these services will also be connected to the Fairley development.
The Barton Highway access intersection is 60% complete, this will provide a new safe access to and from the highway.
There is strong interest in the commercial Village Square and development plans are currently being prepared.
Block sales are going well, with only 5 blocks now available for purchase.
|