Pay close attention when driving in and around the I-25/Cimarron Project. Due to increased truck activity entering and exiting traffic, drivers are urged to slow down, observe speed limits and avoid distractions.
|
The following is a summary of upcoming project construction activity.
Construction schedules are subject to change based on weather/other unforeseen circumstances.
Activity Area
|
Time/date activity scheduled
|
Time/date activity scheduled to end
|
Activity impacts/comments
| Southbound I-25 shoulder closure - Cimarron/US 24 to S. Tejon (mile marker #141 to #140)
|
Sunday, Sept. 27, between 9 p.m. and 5 a.m.
|
Friday, Oct. 2, 5 a.m.
Ongoing throughout October
|
Work will be done Sunday through Thursday evenings.
Hauling material for embankment work. No impact to I-25 travel lanes.
|
Pikes Peak Greenway
Trail
| Currently in place | Detour will be in place throughout October.
| Detour routes clearly marked. Possible intermittent closures of trail throughout the project |
Bear Creek Trail
| Currently in place | Detour will be in place throughout October. |
Detour routes clearly marked.
| Midland Trail
| Currently in place
| Summer of 2017
| Detour routes clearly marked.
|
|
|
How Do I Get Project Updates?
Sign up for periodic project e-newsletters by sending an email to [email protected]
Project alerts are sent via email or text alert. To receive alerts, click www.cotrip.org, then click on the bright green telephone. Scroll down to the "Projects" list for I-25 and Cimarron Interchange.
A telephone hotline is also available at 719-302-6781.
|
What Are The Project Goals? - Maximize overall safety, capacity and operation of the interchange and the surrounding transportation network within the Project budget;
- Complete Project construction to be fully operational before December 1, 2017;
- Minimize impacts and inconvenience to the community, motorists, businesses, downtown and the public during construction; and
- Achieve an aesthetically pleasing design compatible with current and future amenities and enhancements in and around the interchange.
|
Share This Information With Others
Forward this e-newsletter
Please share this information with others who may have an interest in the I-25/Cimarron Interchange Design-Build project. Simply click on the "Forward this email" link below.
|
|
|
|
|