Construction on US-31 from Camp Daggett Road to US-131 began yesterday and is scheduled to continue until the end of September.
The initial primary focus of construction, between Eppler Road and US-131, is to be completed before the 4th of July weekend.
From Eppler Road to US-31
Stage 1 - Eastbound US-31 traffic detoured onto Eppler and Sheridan Roads to US-131 and only one westbound US-31 lane will be shifted to the south side of US-31. The entire north side of US-31 will be built first.
Stage 2 - Westbound US-31 traffic will be shifted to the north side of the roadway, eastbound traffic will continue to be detoured, and the south side of US-31 will be constructed
Stage 3 - A top course of asphalt will be placed in this entire section while maintain the same detour and shifting westbound traffic.
View the project map here.