October 12, 2013
Greetings!
The end is in sight but before we get there, please be advised -- this week TRAFFIC will be messy. As crews prep and pave the road, traffic will be shifted accordingly. Pay attention (and advise your customers) to the flagmen. This will happen up one side and down another, followed by another day or two of road striping and pavement marking. But then, once complete, the road will be OPEN!
Here's what happened last week:
- All brick pavers installed
- All light poles installed
- All irrigation in & ready
- All fencing installed
Coming up this week:
- All structures (drains, catch basins, manholes) raised to street level
- Road leveling complete by mid-week
- Top coat of paving to begin mid-week
- Road striping follows paving
- Landscape material planting begins
- Finish colored concrete
As usual, call 248-546-1632 if you have questions, concerns or ideas on how we can assist you. Looking forward to the end of the road!
Cristina Sheppard-Decius, CMSM
Executive Director
Ferndale DDA