Volume 2013                                                                                                               Issue  12
Looking West on West Nine
  
 FYIs
 Concrete can take up to 5 days to cure. When driveways are being poured, crews pour 1/2 at a time, returning 5 days later to do the second half. A business may request a full driveway pour at one time if preferred.   
 
Concrete CANNOT be poured when temperatures exceed 90 degrees, per MDOT regulations.
 
REMINDER
Get your Wild West Specials to info@downtownferndale.com.  Deadline has been extended to July 8 for distribution that week. Just send in your info and we'll format it.  It's FREE and it reaches 1900+ consumers.
 
Also for motorists, please remember that Beaufield, Dover and Kenton are closed to through traffic at Nine Mile for the remainder of the project.
 
No Meeting Next Week
No construction meeting next week due to the Fourth of July holiday.  The next meeting will be at 11 am, Thursday, July 12 at the DDA Office, 149 W. Nine. 
 
* * * * * * * * *  
Timeline:
How the West 
was One!
 
July * * * * * *
Stage II - GUSSY UP I, North side streetscape enchancements begin.  
ETA - 8 weeks

Sept. * * * * * * *  
Stage III - GUSSY UP II South side Streetscape enchancements begin. 
ETA - 8 weeks
 
November * * * 
GRAND REOPENING! 
Date & Place - TBD 
 
ALL DATES ARE CONTINGENT UPON 
WEATHER & UNFORESEEN SITE CONDITIONS.  
 
* * * * * * * * * * 
June 27,  2013
 

Greetings from West Nine! 

 

We are happy to report that the West Nine Mile water main is now completely in and all businesses are connected to it!  (Cowboy) Hats off to the construction crews who kept the job on schedule, with as few interruptions as possible.  Thank you, too, for your patience during this project.

 

As we enter "Gussy Up" mode, work continues but it won't look like much -- to begin with. But keep watching -- as each step is complete, you will start to see the transformation.

 . 

What to Expect in the Week Ahead:

  • Driveways and sidewalks - work continues.  
  • More base concrete in mainline trench.
  • Grading for sidewalks continues.
  • Crews off road for Fourth of July holiday by 3 pm, July 3.  

 

Again, thank you for your patience.  Call if  the DDA at 248-546-1632 with your questions.   We are here to inform and help!

 

Sincerely, 

 

Cristina Sheppard-Decius, CMSM

 