This update is to inform you that this project is observing the mandatory Holiday Construction Moratorium in La Jolla Village and will resume construction on January 2, 2015
Whereas the main water pipe has been installed, the contractor will be returning to Ivanhoe Rd. to complete small portions of work which includes minor water connections, installing meter boxes, and final paving.
During the next two weeks, the contractor will replace 100-feet of sewer main on West Muirlands Drive between Fay Ave and Nautilus Street. Due to this work, West Muirlands Drive will be closed to non-residents from Monday, December 8th to Monday, December 22nd between 7:30 a.m. to 4 p.m. on weekdays. The street will be open to all on weekends.
Residents will be able to access their properties.
- All residents from 910 -1271 W. Muirlands Drive will need to enter and exit through Fay Ave.
- All residents from 1271-1396 W. Muirlands Drive will need to enter and exit through Nautilus Street.
No street parking will be allowed inside working areas during working hours.