Sewer and Water Group 820
  
Dear Stakeholder  
  

      You are subscribed to received construction updates on the Sewer and Water Group Job 820 project in La Jolla. Click here to see the map of the area involved in this project.

 

Sewer and Water Group 820 construction will resume on Tuesday, September 2, 2014.

 

The work will consist of

  • Resumption of the installation of the water main on Ivanhoe Avenue between Cave Street and Ivanhoe East Ave. This includes trenching in the public right of way.

 

Impacts include

  • Temporary "No Parking" signs will be placed 48 hours before construction activities start. Towing will be enforced.
  • Road closures, detours, and restricted access during work hours are expected
  • Water service during construction will be provided by a 2-inch highline pipe that will run along the curb. Please be cautious when parking along the pipe/curb.

Other Information

  • Hours of Operation - Monday to Friday - 8 a.m. to 4 p.m.
  • Streets will be resurfaced when the entire project in the La Jolla area is completed. The entire project is anticipated to be complete in April 2015.

 

     Thank you for your patience and understanding while work progresses on this project. Every provision will be taken to quickly and efficiently complete the work.

 

      Please encourage your neighbors to join our mailing list! And use the Forward feature to pass along this important information.