Avenida De La Playa Infrastructure Replacement Project & Sewer and Water Group 809 |
You are subscribed to received construction updates on the Avenida De La Playa Infrastructure Replacement Project and Sewer and Water Group Job 809.
- Culvert boxes on Avenida De La Playa just west of Camino Del Sol have been reset at the proper depth. 12 boxes remain and work will resume after the summer moratorium.
- The new water main has been installed and capped just west of Camino Del Sol on Avenida De La Playa. This work will resume after the summer moratorium.
- The existing highlines will be removed on Thursday, May 22.
- Curb, gutter and street repair on Avenida De La Playa west of Camino Del Sol will take place daily through Friday, May 23.
- At and near the outfall structure: concrete pour of the boardwalk and sea wall staining will continue for the next week.
- For Group Job 809, sewer main and lateral installation on Paseo Del Ocaso from Avenida De La Playa to Vallecitos will continue through May 23.
- On Tuesday, May 20, archeological exploration of St. Louis Terrace, La Jota Way and Hypatia Way will end and the trench plates will remain during the summer moratorium based on the archeological requirement.
- On Tuesday, May 27, construction activity for Group Job 809 will shift to the east of La Jolla Shores Drive on Vallecitos, Avenida De La Playa and Paseo Dorado.
Thank you to the community for your patience and understanding while work progresses on this project. Every provision will be taken to quickly and efficiently complete the work.
Please encourage your neighbors to join our mailing list and use the Forward feature to pass along this important information! |
|
|
|
For questions related to this project,
|
|
|
|