We need to remember that scheduling is very high on the list of important issues.
Work Safely,
Jim Thompson Executive Editor
|
|
_______
Scheduling
I was recently reminded how important scheduling is, no matter the size of the project. In fact, if it is more than installing one bolt, your project needs a schedule. When do you start the scheduling process? Absolutely as early as possible. If it is a large project, you will start the scheduling process before you receive capital authorization. Schedule impacts costs, even if everything goes right. There are many ways to do the same tasks that are impactful, good or bad, on the schedule. Even if everything clicks absolutely perfectly, there will be a shorter way to do a project making certain choices that is optimal to another way. When I was a young engineer working in a converting plant that worked only five days per week, I had this driven home to me. We were going to make a change in a certain piece of machinery on Friday night after the last shift of the week. We thought it was minor. However, we had not carefully scheduled it and accounted for every step. We had not double checked our parts list. Three simple bolts, unobtainable after midnight Friday in this rural location, prevented us from doing any of the project. Monday morning we looked foolish and all involved had black marks against our names. And, the next Friday night we got to do the whole thing over again (of course, I made sure we had a box of those stupid bolts--I was prepared to lose or twist off about twenty-five bolts and still have a successful project). A few years later, not so many miles away, I was involved in a very large papermachine rebuild. The construction contract, despite my protestations, had been let as a firm lump sum. Three months before the shutdown, the contractor mobilized. The contractor's scheduler showed up with the entire schedule on two sheets of drawing paper (this was still before computerized scheduling). I was horrified at the shallowness of his work and raised an alarm with anyone who had a remote chance of listening. To no avail. And I was correct. The scheduled downtime was a disaster, even though the contractor faced a punitive penalty for every day he was late. I have learned scheduling is high on the list of the important issues. I hope you have, too.
|
________
Current Patent Activity is available here.
|
________
Capital Arguments Engineering Manager of the Year Hall of Fame
Since its inception, Capital Arguments has believed extraordinary projects are possible. They can be done safely, responsibly and offer a great advantage to their mills with lower capital costs and saved downtime. We established this award in 2008 to recognize those people and companies that follow this philosophy. This award is given once per year somewhere in the world. We honor our inductees permanently here.________
Ed Kersey--Engineering Manager of the Year 2011
Jim presents Ed with the Engineering Manager of the Year for 2011. (L - R) Matt Nilsen, Jim Thompson, Ed Kersey and Wayne South. Nilsen is Account Manager and South is Business Development Manager for Kadant Black Clawson, underwriter of this year's award. Kadant Black Clawson was a major sponsor of the 2011 Award. Here, on the left, Peter Flynn, President of Kadant Black Clawson, receives the company's duplicate of Ed's Award from Steve Roush, Publisher and Editor, Paperitalo Publications. ________
Not Awarded 2010You have to be really good to get this award. We did not receive any qualified nominees in 2010.________
Dean Abrams--Engineering Manager of the Year 2009
Now retired, Dean was an engineer at Corrugated Services, Forney, Texas, USA in the summer of 2009 when he completed his award winning project. Dean managed a team that installed a secondary headbox in 11 hours, 30 minutes, paper-to-paper. The experts had said it would take at least 3 days. In April 2010, we presented the award to Dean in the presence of a number of his colleagues.
Here is the award we presented to Dean:
Mike Ahcan--Engineering Manager of the Year 2008
Mike works at the UPM Blandin Mill in Grand Rapids, Minnesota, USA. In 2008, the mill's sole effluent pipe, running outside a building, almost in the Mississippi River, was determined to be in a state of imminent collapse. The experts said it would take a week of total mill downtime to replace it. Additionally, there was a danger of leakage into the river. Mike and his team went to work and replaced the pipe without any downtime and with no spillage. We had a banquet in Grand Rapids for him in July 2009.
And here is Mike's award:
We normally accept nominations in the November-December time frame. They can be sent to jthompson@taii.com with "EMOY Nomination" in the subject line.
|
|
|
Please write when we tickle your brain cells! Email jthompson@taii.com
|
|
|
________
Early bird registration for the 2013 Conference (Jan 20 -22) is open. Click on the Logo for information.
|
________
Currently in 3rd printing. Almost 500 copies in the field since 2006!
|
|