April 1, 2015


AIRFIELD CONSTRUCTION SCHEDULED TO BEGIN MONDAY, APRIL 6
 


As part of the Runway 13/31 reconstruction project, a runway and several taxiway closures are scheduled to begin Monday, April 6.

A NOTAM will be posted immediately and crews will be on-site by 7:00 am to set up barricades and other closure and safety equipment. 

Runways 8/26 and 17/35 will remain open during this phase of construction but it will be necessary to backtaxi to depart from Runway 17.

During this time, please continue to check NOTAMs. We will attempt to keep you as up-to-date as possible via newsletters and our Facebook and Twitter pages.

CLOSURES
  • All of Runway 13/31
  • All of Taxiway Juliet
  • Taxiways Bravo and Charlie between Runway 8/26 and Taxiway Juliet

SCHEDULE
Please note that the schedule is weather dependent.
  • Closures begin Monday, April 6
  • Taxiway Juliet scheduled to reopen toward the end of May. (Runway 13/31 will remain closed for the entire length of the project.)
  • Project end date scheduled for Monday, August 3

CONSTRUCTION DETAILS
For this phase, the following construction activities will occur:
  • Construct run-up area at Taxiway Charlie and Taxiway Juliet intersection
  • Rehabilitate Runway 13/31 between Taxiway Juliet and Runway 8/26
  • Rehabilitate Taxiway Juliet between the hold short lines on either side of Runway 13/31
  • Replace runway and taxiway lights and signs
  • Install Runway 13 PAPI

San Marcos Regional Airport is professionally managed by Texas Aviation Partners. Visit our website for more information or call (512) 216-6042.