Lean Construction Header
7th Edition   
 
The topics for this edition are:
  • The Complete Master Schedule as Part of Lean Project Scheduling (PS)
  • The Misuse of Lean Kaizen Events 

Lean Construction Overview

One-Day Training Sessions

 

June 24th - Milwaukee

June 27th - Chicago

July 21st - Fort Wayne 

 

A recent session attendee, Chris Johnson, President of Piper Fire Protection said, "This class was a real life changer for me."  

  

View the training sessions, location, and pricing at 

www.wcmfg.com/LeanConstruction.htm  

The Complete Master Schedule as

Part of Lean Project Scheduling (PS)

The value of the traditional Master Schedule is substantially enhanced when it includes a Phase Plan.


by Dennis Sowards

Traditionally, all major projects have a Master Schedule. It is usually developed in great detail with much thought by the general contractor's project engineer or scheduler. It is useful in finalizing the overall job plans and proving that the job can meet the owner's deadline requirements. One of the fun discussion questions I love to ask when teaching about Lean Project Scheduling is, "How long is the master schedule still accurate once the project begins?" Answers range from days to hours to minutes to "it never was!" The Master Schedule often ends up in the corner of a job trailer - useless for real Project Scheduling.

 

Why the "traditional" Master Schedule is not enough

 

The Master Schedule is a point in time forecast and suffers from the fact that almost all forecasts are wrong. Trying to accurately predict the work schedule months and even years into the future is very difficult. The longer the forecast timeframe, the less chance it has of modeling reality. The more detailed one tries to make the plan the greater the chance it will be wrong. On the other hand, the closer to doing the actual work, the more accurate a plan can be. Since projects are a team effort involving many trades, it is very difficult for one person, no matter how experienced, to accurately define each trade's tasks and time requirements.

 

Lean Project Scheduling (PS)

 

The purpose of the PS is to empower the workforce to work together as a team, through frequent 2-way project communication, and by allowing the team to take ownership and responsibility for their work as well as the project's milestones and goals.

 

PS contains five components:

 

1)    Master Schedule - identifies overall activities, sets milestones, and develops Phase Plans to accomplish those milestones

2)    Six-Week Schedule - a look into the future so bottle-necks, limiting factors, and roadblocks can be identified in advance

3)    Weekly Schedule - a plan of what will be done (includes "Daily Huddle")

4)    Weekly Scorecard - what we committed to vs. accomplishments (includes PS meeting) 

5)    Continuous Improvement Review - what can we do better in the entire process?

 

PS Master Schedule - a More Complete and Collaborative Alternative

 

The Master Schedule is useful in providing a big picture of the schedule for the owner. The second part of the Master Schedule is called a "Phase Plan." This is a more detailed and accurate plan that is required for execution. It is developed in a collaborative meeting. By engaging those who will construct the facility in a "phase" soon to be done, the forecast can be more accurate and detailed. During this phase planning session the team will also identify and remove constraints they see as barriers in doing the work. Finally, since developing the phase plan is a team effort, commitments are made and ownership is taken, that is not realized when one person formulates a Master Schedule.

 

A phase plan should be prepared close to the start of that phase, but early enough to make work ready and assure coordination. Typically, phase plans are prepared at least six weeks prior to the start of the first activity and even sooner if longer lead times have been identified. The ideal way to do phase planning is for the general contractor to lead the session and involve all trades responsible for the work in the specific phase.

 

Done in Reverse

 

Phase schedules are best developed using 'reverse planning.' This is done by the team reviewing the Master Schedule and appropriate milestones and defining the work in tasks and sequence. Then the team starts with the last task in the phase to be completed and works back to identify the work needed to complete it. Next, they identify all tasks that must be completed to do the next-to-the-last task, and continuing backward to the beginning of the phase. This back-to-front process identifies the conditions required for work to be released from one activity or task to the next and the coordination necessary to allow multiple activities to proceed concurrently.

 

This process is best done on a blank wall. Participants add sticky notes for each activity and move these around as new work or other trades add tasks and new relationships are revealed. Each trade or craft writes a brief description of the work/tasks they must perform to complete this phase - one task per sticky note. Each trade will use a different color of sticky pads. They identify what they will "give," meaning the task they do that will release work to the next task (done either by them or another trade). On the same sticky they also identify the task they need to "get," that must be completed by others to release the work to them. The sticky notes (tasks) also contain a time estimate (duration) to perform that work. These tasks represent the "should do" tasks for the project during each phase.

 

A rough time scale is established so people have a sense of the timing of all the tasks. This is a very participative process with much negotiating. Activities in a phase schedule are highly dependent on each other. They involve routine and repetitive interfaces between trades and therefore require close coordination. The phase schedule identifies the rules for release of work from one activity to the next. An experienced neutral facilitator can help the process go smoothly.

 

Durations should be established for each task/activity. The durations themselves should represent the most likely time to do the task given the circumstances on the project and the knowledgeable trade partner's estimate of their ability to be reliable. Durations should not include float or contingency time typically added by foremen in reporting the time to perform. The total time to do the phase is the sum of the critical durations of these tasks.  The durations will establish the critical path through the phase and, in most cases, float within the phase will become apparent. The team should allocate float time to the most uncertain activities in order to assure that the proper timing of activities remains stable.

 

If the project is pressed for speed and shortening the schedule is desired, the team should explore how the phase can be accelerated. It should look at what actions will be required, and how the group will respond to early completions.  By contrast, if the work in a phase exceeds the available duration, the team must carefully consider alternatives and their costs and open negotiations at the project level in order to best achieve project objectives.

 

A typical phase scheduling session will take a few hours although the time can be shortened if the team is experienced and/or templates from similar work are available.

 

A project may have as few as three to as many as 10 to 15 phases depending on the scope and size of the job.

 

Some phase plan session tips are:

 

1.       Learn in action. Phase planning is not typically done in construction and will feel uncomfortable at first, especially developing the schedule as a multi-trade team. Like learning to ride a bicycle, it takes "doing" to gain confidence.

2.      Make sure you have the right people in the session. All trades involved in work during that phase should participate.

3.      Prepare people for the session by training them in "why" and "how" the process works and what they need to bring to the meeting. Basic Lean training on the concepts of value, waste and flow is helpful.

4.      Have the project drawings available so questions can be answered quickly

5.      Do small phases, especially at first, to gain confidence.

6.      Work from the end (last task) back - plan from the future.

7.      Clarify hand-off criteria (rules of release) and interactions.

8.     Encourage debate and discussion.

9.      Work to make the phase doable within the milestone.  This may require a change in the hand-off criteria.

10.  At the end of the session, identify the next phase and when it will be planned.

 

If only one or more subcontractors are applying the Lean Project scheduling method without the G/C leading and/or other trades participating, the pulling planning process' effectiveness is limited. But it can still help the trade or trades involved to have a better understanding of their part of each phase and the critical hand-off requirements. It is still worth doing.

  

In summary, the traditional Master Schedule is limited in its usefulness. It should be done to show the major milestones, but not in great detail. A PS Phase Plan should be included as part of the Master Schedule. It includes activities planned in a team effort coordinating the handoffs to make the workflow. Reliability, much needed in doing construction projects, is achieved by collaborative planning and fulfilling promises made by those who will do the work.

 

 

Your Lean Construction Journey Starts with a Company Lean Assessment

 

Contact us for a Lean Assessment proposal

WCM Associates LLC

www.wcmfg.com

260-637-8064 

The Misuse of Lean Kaizen Events

Stop doing Kaizen Events that are not tied into your organizations goals!

 

by Larry Rubrich

 

Kaizen Events are a powerful Lean improvement tool! Like Value Stream Mapping, Kaizen Events unfortunately are often misused. They have become an "end all" to themselves. Organizations do Kaizen Events just to do them, even budgeting the number they will do in a year (this is nonsense!). These events are often called spot, point, or drive-by Kaizen Events. Stop doing them!! 


When examined, organizations are found to have hundreds of areas where improvements are possible by eliminating waste! How do you know where to start? 

The answer is to use Kaizen Events to focus only on the improvements which support achieving the organization's current goals, plans, or budget. This strategy prevents us from using resources and time for an improvement activity that is currently not on top management's radar (leaving top management wondering what Lean is doing for them). 

Lean and Kaizen Events must be used and seen by top management and the entire organization as the "system" by which the company achieves its goals. This is accomplished using Hoshin Kanri or Policy Deployment. Policy Deployment links all improvement activities with the organization's goals. It is this lack of linkage which causes most American organizations to fail at successfully sustaining Lean.   
  
Kaizen Events should ultimately be scheduled using this "pull" from Policy Deployment strategy. Early on in the Policy Deployment Lean implementation plan, it may be necessary for the company's Lean Facilitator to "push" or tell a particular area to do a Kaizen Event. This may be based on a particular team operating below their "committed to" goal (which supports the achievement of the organization's goals). Once all the teams and areas of an organization "own" their goals and measurements, they will pull Kaizen Event help from the Lean Facilitator when they find themselves off target. 
  
This Lean newsletter is the result of the collaboration of three organizations:
 
Grunau Company
Ted Angelo, Executive Vice President

Quality Support Services, Inc.
Dennis Sowards, President
[email protected]

 

WCM Associates LLC
Larry Rubrich, President

 

Please give us feedback with your thoughts and ideas for this newsletter!
Integrated Project Delivery is a Trademark of Westbrook Commercial Services
 
Larry Rubrich
WCM Associates LLC
� 2011 WCM Associates
 
Join Our Mailing List