A major milestone has been achieved at Barton Place with all six buildings obtaining Final Certificate of Occupancy. This means all City inspections have cleared with regard to electrical, plumbing, mechanical, and fire safety. At this stage new residents have started moving-in and are already taking advantage of the completed amenities, such as the outdoor grilling areas, gym, resident lounge, and heated saltwater pool - residents were actually doing laps this past weekend. Below is a snapshot of the most recent progress:
Building 6 & 5: Achieved CO (Certificate of Occupancy) October 21, 2010
· Landscape maintenance and touch-ups continuing
· Artwork and plants installed in corridors
· Rooftop terrace and grill completed
· Scheduled HOA maintenance & cleaning underway
Building 4 & 3: Achieved CO (Certificate of Occupancy) November 4, 2010
· Landscape maintenance and touch-ups continuing
· Completing final sign-off of interior & exterior quality inspection items with White Construction
· Artwork installed in corridors
· Plants to be installed in corridors within 4 weeks
· Rooftop terrace and grill completed
· Scheduled HOA maintenance & cleaning underway
Building 2: Achieved CO (Certificate of Occupancy) December 15, 2010
· Landscape maintenance and touch-ups to begin
· Quality-control inspection completed with final sign-off and acceptance to begin
· Artwork and plants to be installed in corridors within 4 weeks
· Scheduled HOA maintenance & cleaning to begin
Building 1: Achieved CO (Certificate of Occupancy) January 6, 2010
· Landscape maintenance and touch-ups to begin
· Quality-control inspections completed with final sign-off and acceptance to begin
· Artwork and plants to be installed in corridors within 5 weeks
· Scheduled HOA maintenance & cleaning to begin
Garage Parking: Garage cleaning and maintenance is underway. White Construction will begin to clear out material and equipment upon completion of final sign-off inspections in buildings 1 & 2. This is anticipated to occur in mid-February.
Landscaping: A revised landscaping plan is under review by the development team that will include a shaded seating area and new plantings beneath the Big Ole Pecan between buildings 2 & 4.
Austin Energy Green Building: We're working with the Architects and consultants for submission to AEGB to achieve a 3-Star green building rating.
Site monitoring & security:
A full camera system and on-site monitoring system have been installed throughout the garage and perimeter of Barton Place. In addition, a guard-house has been added at the north entry whereby 24 hour personnel are available to great vendors, receive packages, and assist residents.