The following is the proposed schedule provided by Pan Am Railways to complete the railroad grade crossing reconstruction work. Each crossing will require a full 36 hour closure to allow for replacement and re-alignment of the track panel, as well as preparation and placement of final pavement:
Mon. 8/15 - Tues. 8/16 Bow Street Crossing 
Wed. 8/17 - Thur. 8/18 West Street Crossing
Mon. 8/22 - Wed. 8/23 School Street Crossing
Mon. 8/29 - Tues. 8/30 East Street Crossing
Wed. 8/31 - Thur. 9/1 Webster Road Crossing
Tues. 9/6 - Wed. 9/7 Hunter Rd. (Porter Rd)
Thur. 9/8 - Fri. 9/9 Upper Mast Road
Tues. 10/3 - Wed 10/4 Fernald St. (Hall Rd.)
Bow Street Construction is on schedule. It is anticipated that the road will be open to vehicular traffic at approximately 7:00 pm on Tuesday, August 16, 2011.
If there are any questions about the proposed road closure schedule, please contact Sande Updegraph with FEDC. |