Week 12 Quality Report
Physical Inspection - 67% Accepted
Electrical Testing - 70% Passed
In the 12th week of 2011, White Horse facilitated USD91,813.00 in reliable component purchases.
Week 12 saw another improvements in both physical inspection and electrical testing yields. With 37% of devices being physically substandard, not a lot was moved beyond inspection and into testing.
- Xilinx XC4010XL-2PQ100C, 22% failure (Date Code 0525) - programming failure in JTAGtesting and Vcc shorted to GND.
- Xilinx XC17SO5XLPD8C, 43% failure (Date Codes 0913) - ID error.
- International Rectifier IRAMX20UP60A-2, 15% failure (no date code marked on parts or labels) - incorrect outputs and missing/broken pins.
|