  • Emergency sprinkler installation continued throughout the garage, along with the painting of door frames. Concrete touch ups and soil fill-ins around the sides of the garage continued, as did the waterproofing of the garage roof and the south wall.
  • The installation of elevator equipment, storm piping, and insulation continued in both the southwest and northwest elevator stations.
  • Construction of the permanent stage on the northern edge of the Civic Lawn progressed.
  • Landscaping continued around the playground.
  • Preparation for sidewalk pours continued in front of the restroom building.
  • Installation of pump room equipment continued, while storm system installation continued at 14th Street.
  • The waterproofing system installation for the expansion joint on Race Street also continued.
  • Preparation for the east ramp concrete pour continued.
  • Preparation for sidewalk pours will continue along Elm Street.
  • Light pole base construction was completed throughout the southeast region of the park.

 

To see construction photos from this week, please click HERE.

 


Next Week in the Park
February 13 - February 17, 2012
  • Emergency sprinkler and storm system installation will continue throughout the garage and the perimeter. Waterproofing will continue on the roof and soil backfill will continue around the perimeter of the garage.
  • Equipment installation and waterproofing will continue in the elevator stations.
  • Concrete finishes and touch ups will continue.
  • Stage construction will continue.
  • Sidewalk pours around the restroom building will begin.
  • Construction and soil fill-in work on and around the concession buildings will continue.
  • Fence installation will begin around the dog park.
  • The pump room equipment installation will continue.
  • Storm system piping installation will continue on Race Street, as will the prepping of the Elm Street ramp for future concrete work.
  • Light pole installation and the setting of sandstone platforms will continue in the south end of the park.
About 3CDC

3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community.  3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood.  3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF).  These investment funds play an important role by providing needed financial capital to 3CDC's development projects.  For more information visit www.3cdc.org.