This Week in the Park January 9 - January 13, 2012
- Emergency sprinkler system piping, storm piping, and electrical wiring installation continued throughout the garage. The HVAC duct continued to be installed and select concrete touch ups took place. The garage lid continued to be waterproofed.
- Glass installation began in the northwest elevator portal and preparation for elevator installation continued in the southwest elevator portal. Steel and decking work also continued in both the northwest and southwest elevator portals.
- The trellis of the Restroom Facility continued to be primed and painted.
- Preparation for the installation of pump room equipment began, while storm system installation began on Race & 14th Streets.
- The installation of the domestic water main continued and the installation the waterproofing system for the expansion joint on Race Street also continued.
- Form structure removal from the ramp lid pours continued.
- The installation of light poles continued in the south end of the park.
To see construction photos from this week, please click HERE.
|
|
Next Week in the Park January 16 - January 20, 2012 - Sprinkler system and storm system piping installation will continue throughout the garage. The installation of steel tubing will begin on the second floor of the garage. Also, the installation of elevator components is set to begin in both landing portals.
- Waterproofing installation will continue in the northeast elevator portal, while steel and decking work continues in the southwest elevator portal.
- Select concrete area finishes and touch ups will continue.
- Installation of engineered mulch will continue around the playground castle.
- Fence installation will begin around the dog park.
- Installation of pump room equipment will begin.
- Storm system piping installation will continue on Race Street. The installation of the domestic water main will also continue, as will the prepping of the Elm Street ramp for a future SOG pour.
- Light pole installation and the setting of sandstone plinths will continue in the south end of the park.
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|