This Week in the Park
September 6 - September 9, 2011
- The garage is approximately 70% complete. This past week, rebar was installed for upcoming roof pours. All columns in the in the garage are now complete. Conduit continued to be set up throughout the lower level of the garage as well as waterproofing of the south wall.
- The solar tube installation in the restroom building is now complete and the storefront has started to be installed.
- The porphyry installation around the bandstand continued.
- The fountain located in the dog park continued to be installed.
- The south end continued to be prepped for planting beds and the sidewalk along Elm Street was removed.
To see construction photos from this week, please click HERE. |
|
|
Next Week in the Park
September 12 - September 16, 2011
- In the garage, rebar and form installation for the roof pours will continue. The foundation will begin to form for the pump room. Plumbing and electrical work will proceed in the lower level of the garage as well as waterproofing the double sided wall.
- Drywall installation in the restroom building will continue.
- In the south end, curb and concrete work as well as sidewalk pours will continue.
- Continue to irrigate and prepare the site for sod installation.
- The playground castle will be delivered to the site within the week.
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|