August 29 - September 2, 2011
- Progress in the garage continues. The first pour of concrete for the roof/plaza level of the garage was made on Thursday morning. Rebar installation continued for additional concrete pours on the roof and for columns within the garage. Conduit continued to be installed in the lower levels of the garage as well as waterproofing along the south garage wall.
- Drywall installation began in the restroom building as well as solar tube installation.
- The dog fountain installation continued in the dog park
- The porphyry installation around the bandstand continued
- In the southern end, irrigation installation continued as well as prepping for the planting beds. The sidewalk at the 12th Street entrance was poured and the canon was set on the foundation block.
To see construction photos from this week, please click HERE. |
|
|
Next Week in the Park
September 6 - September 9, 2011
- Next week in the garage, rebar continues to be installed as well as installation of the roof deck forms. Columns for the plaza level of the garage will be constructed, and plumbing and electrical work in the lower level of the garage will continue.Waterproofing installation continues.
- In the south end of the park, sidewalks continue to be poured as well as curbs. Preparation work for sod will begin and irrigation installation will continue.
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|