This Week in the Park
July 11 - July 15, 2011
- Completed garage wall pours along Race Street
- Poured third deck of garage
- Completed south lower level wall pours of garage
- Completed fifth slab on grade pour in garage
- Set up rebar for next deck and slab pours in garage
- Completed installation of base for Tivoli light foundations surrounding the bandstand
- Exposed aggregate poured in areas of dog park
- Completed curbs for perimeter of dog park
- Continued underground drainage in garage
- Began metal framing installation at restroom building
- Began filling in interior ramp of garage
- Underground electric and storm drainage installed at playground
- Began piping installation for water runnel
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
July 18 - July 22, 2011
- Continue to tie rebar cages for garage deck pours
- Install footers for playground canal boat
- Continue piping installation for water runnel
- Continue roof termination and parapets at restroom building
- Continue utility work in the south end of park
- Begin pouring outer curb around the bandstand
- Continue under slab drainage under garage
- Sixth slab on grade pour for garage
- Fourth deck pour in garage
- Sidewalk pour south of the bandstand
- Continue to install forms for deck pours
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|