  • Under-drain utility installation south of bandstand continues 
  • Waterproofing continues along 14th Street  
  • Concrete pile caps and columns poured on Elm Street side 
  • Auger cast piles completed 
  • Set first door frame at restroom building 
  • Block walls begun at the restroom building 
  • Water line installed to dog park 
  • Layout of dog park continues
  • Layout of curb surrounding bandstand 
  • Asphalt removal on Race and 12th streets for curb
  • First two sections of garage wall poured along Elm Street   

To see construction photos from this week, please click HERE.   

Next Week in the Park
May 16 - 20, 2011

  • Continue to tie rebar cages and pile caps pours 
  • Third and fourth wall pours for garage along Elm Street 
  • PVC drains installed in waterproofing 
  • Continue utility and underdrain work in the south end of park 
  • Continue waterproofing installation along 14th Street 
  • Begin garage under drain and sump pits 
  • Continue block walls at restroom building 
  • Playground layout and grading of playground area 
  • Finish elevator pit in the northeast corner   
About 3CDC

3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community.  3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood.  3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF).  These investment funds play an important role by providing needed financial capital to 3CDC's development projects.  For more information visit www.3cdc.org.


3CDC
Christy Samad
Communications Officer
513.621.4400 ext 120
513.307.2739 (cell)
csamad@3cdc.org