This Week in the Park
May 2 - May 6, 2011
- Under-drain installation southeast of bandstand
- Concrete pile caps and beams poured along Elm Street
- Auger cast piles to be 95% complete
- Rough grading continues on south end
- Water line installed to dog park
- Layout of dog park
- Layout of curb at bandstand
- Slab on grade poured in comfort station
- Electrical re-wiring of the bandstand
- First wall pour for garage construction along Elm Street
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
May 9 - 13, 2011
- Continue pile cap and garage foundation construction
- Second wall pour along garage perimeter
- Finish mass excavation
- Under drains placed in south end of the park
- Waterproof membrane installation continues along 14th Street
- Continue restroom building construction
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|