This Week in the Park
April 25 - April 29, 2011
- Under-drain installation southeast of bandstand
- Granite curb removal on Race Street to mid 12th Street
- Reinforcement placed in the waterproofing along A line (Elm Street)
- Thermal & moisture protection installed in comfort station
- Elevator jack-holes drilled
- Concrete pile caps and beams poured on A line
- Conduit installation underneath the bandstand
- Auger cast piles drilled on the East side of garage
- Water line installed from Race Street to bandstand
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
May 2 - 6, 2011
- Contractor to deliver form work for walls
- Beam and pile cap pours continue along the northwest garage
- Auger cast pile installation to be completed
- Electrical re-wiring of the bandstand
- Under drains placed in the southwest to continue
- Slab on grade pour in comfort station
- Rough grading of south
- Layout of dog park
- Layout of curb at bandstand
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|