This Week in the Park
April 18 - April 22, 2011
- Completed foundation block walls at restroom building - including waterproofing
- Completed conduit installation at restroom building
- Continued mass excavation throughout the site
- Continued waterproofing installation along garage walls
- Continued storm drainage system throughout the south end of the park
- Continued installation of elevator jack holes for garage construction
- Began pile cap construction and installation for garage foundation
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
April 25 - 29, 2011
- Finalize and complete mass excavation - weather permitting
- Continue auger cast pile installation
- Continue waterproofing installation along garage walls
- Continue underground utility work
- Continue restroom building above ground construction and pour floor slab
- Continue pile cap and garage foundation work
- Continue sidewalk work along Race Street
- Begin sub-grade base and slab installation around bandstand
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|