WASHINGTON PARK UPDATE
April 8, 2011

This Week in the Park
  April 4 - April 8, 2011

  • Completed foundation for the restroom building and began constructing walls
  • Continued playground foundation and curb installation
  • Continued installing auger cast piles
  • Continued final stages of lagging board installation to 30 feet deep (final depth)
  • Continued mass excavation throughout the site
  • Continued waterproofing installation
  • Began installation of storm drainage system throughout the south end of the park
  • Completed site demolition around the bandstand

To see construction photos from this week, please click HERE.   

Next Week in the Park
April 11 - 15, 2011

  • Continue 2nd lift of mass excavation to 30 feet deep (final depth)
  • Continue auger cast pile installation
  • Continue waterproofing installation
  • Continue underground utility work
  • Continue restroom building above ground construction, including utility work 
  • Mobilize baker concrete and begin pile cap installation on the Elm Street side
  • Continue sidewalk work along Race Street
About 3CDC

3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community.  3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood.  3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF).  These investment funds play an important role by providing needed financial capital to 3CDC's development projects.  For more information visit www.3cdc.org.


3CDC
Christy Samad
Communications Officer
513.621.4400 ext 120
513.307.2739 (cell)
csamad@3cdc.org