This Week in the Park
March 28 - April 1, 2011
- Selected all the future trees for the park
- Constructed curbing and foundations for the playground
- Formed footers and foundations for the new restroom building
- Continued installing auger cast piles - currently 50% complete
- Continued final stages of lagging board installation to 30 feet deep (final depth)
- Continued mass excavation throughout the site
- Continued waterproofing installation
- Completed side walk demolition along Race Street between 12th and 13th streets
- Finished dry well installation and began next round of underground utility work
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
April 4 - 8, 2011
- Continue 2nd lift of mass excavation to 30 feet deep (final depth)
- Continue auger cast pile installation
- Continue waterproofing installation
- Continue underground utility work
- Finish restroom foundations and begin constructing block walls
- Commence site demolition around Bandstand
- Continue sidewalk work along Race Street
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|