This Week in the Park
March 21 - 25, 2011
- Completed installation of four dry wells and began installation of fifth (last) dry well
- Completed the layout for the 13th Street restroom station
- Continued final stages of lagging board installation to 30 feet deep (final depth)
- Continued restoration of historic features
- Began the installation of the auger cast piles
- Began the waterproofing installation for the garage
- Began tying rebar cages for the foundation pile caps under the garage
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
March 28 - 31, 2011
- Continue 2nd lift of mass excavation to 30 feet deep (final depth)
- Continue final lagging board installation to final depth elevation
- Complete fifth (final) dry well installation
- Continue restoration of historic features
- Continue installation for auger cast piles
- Continue tying rebar cages for the foundation pile caps under the garage
- Begin installation of footers for the 13th Street restroom station
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|