This Week in the Park
February 7 - 11, 2011
- Drilled and installed tie-backs on retention walls along Race Street
- Continued lagging board installation to tie-back elevation along Race Street
- Continued mass excavation in the middle of the garage area and along the northern and eastern perimeter walls
- Completed construction access road to the bottom level of the garage (30 feet deep)
- Continued survey and general layout on south side of park
- Capped existing utilities in the south end of the park
- Began removal and restoration of historic columns in the south end of the park
- Began removal and restoration of perimeter limestone wall along Race Street
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
February 14 - 18, 2011
- Finalize drilling and installing tie-backs on retention walls along Race Street
- Continue lagging board installation to tie-back elevation along Race Street
- Continue 2nd lift of mass excavation to 30 feet deep (final depth)
- Haul off mass excavation dirt (weather permitting)
- Continue layout and survey at south end of the park
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|