This Week in the Park
January 17 - 21, 2011
- Continued mass excavation for the garage
- Continued retaining wall installation for garage construction - including lagging boards and tie-backs
- Continued asphalt and concrete pathway removal on the south end of the park
- Began survey and layout on the south end of the park
To see construction photos from this week, please click HERE.
|
|
|
Next Week in the Park
January 24 - 28, 2011
- Drill and install tie-backs on retention walls on the north wall along 14th Street
- Continue lagging board installation to tie-back elevation on the north side of the site along 14th Street
- Mass excavation in south end of garage working west to east
- Haul off mass excavation soils (weather permitting)
- Continue asphalt path removal in south side of park
- Remove tree debris from site
- Continue installation of temporary electric service to the site
- Continue survey and general layout on south side of park
|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|