Next Week in the Park
January 3 - January 7, 2011
- Continue H piles and shoring system (shoring walls for the garage) installation
- Continue mass excavation for garage
- Move construction fence to south end of site on Wednesday, January 5th (see map below)
- Tree preservation work
- root pruning, tree-trimming, and winter fertilization
- Existing walkway pavement demolition
- Begin dry well installation
- General laying out of the project
- Initial site re-grading
- Begin initial footings/foundations for playground
- Begin underground drainage and plumbing work

|
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|