City of Cincinnati                 Cincinnati Parks              3CDC
WASHINGTON PARK UPDATE
December 31, 2010

This Week in the Park
December 27 - 31, 2010

  • Continue H piles and shoring system (shoring walls for the garage) installation
  • Continue mass excavation for garage
               wp 1 wp 2
               wp 3 wp 4

 
Next Week in the Park
January 3 - January 7, 2011
  • Continue H piles and shoring system (shoring walls for the garage) installation
  • Continue mass excavation for garage
  • Move construction fence to south end of site on Wednesday, January 5th (see map below)
    • Tree preservation work
      • root pruning, tree-trimming, and winter fertilization
    • Existing walkway pavement demolition
    • Begin dry well installation
    • General laying out of the project
      • surverying and staking
    • Initial site re-grading
    • Begin initial footings/foundations for playground
    • Begin underground drainage and plumbing work
Fence move


About 3CDC

3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community.  3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood.  3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF).  These investment funds play an important role by providing needed financial capital to 3CDC's development projects.  For more information visit www.3cdc.org.


3CDC
Christy Samad
Communications Assistant
513.621.4400 ext 120
513.307.2739 (cell)
csamad@3cdc.org