|
This Week in the Park
December 6 - 10, 2010
- Off-site tree relocation work is complete
- Tree preservation work has begun
- Pool building is 95% demolished
- The crane needed for the shoring system has been delivered and erected
- H-Piles for the shoring and retention wall for the garage have been delivered
 
|
Next Week in the Park December 13 - 17, 2010
- Finish demolition of pool pump house & pool structure
- Begin mass excavation of Garage
- Set up crane for temporary pile drilling
- Begin drilling temporary shoring piles
- Tree removal and logging of trees within fenced in area
- Install Turner/Megen office trailer on Elm Street
- Continue fertilization and pruning of trees to remain
- Groundbreaking ceremony on Friday, Dec 17th at 2pm
|
 |
About 3CDC
3CDC is a private, non-profit, real estate development and finance corporation focused on revitalizing Cincinnati's urban core in partnership with the City of Cincinnati and the Cincinnati corporate community. 3CDC's work is specifically focused on the Central Business District and in the Over-the-Rhine neighborhood. 3CDC also manages The Cincinnati Equity Fund (CEF) and the Cincinnati New Markets Fund (CNMF). These investment funds play an important role by providing needed financial capital to 3CDC's development projects. For more information visit www.3cdc.org.
|