Correct Green Logo


WACO CONVENTION CENTER
RENOVATION UPDATE NEWSLETTER
May 2010
renovation pc
 
 
The newest photo album shows the
 progress made on the renovation. It is located at:
 

Upper Level Progress


Upper Level Rooms

 

Chisholm Hall has been completely repainted in a neutral color. The balcony is now enclosed and painted. The stage and drapes have been removed, and the area where the stage was located has been painted black. The stage is portable equipment and may be used in that location for any event that require it, just as it was previously. New restrooms are being constructed outside the hall, in the area where the concession stand formerly stood.

 

In McLennan Hall, the chair rail has been removed and the room has been repainted. Bosque Theatre and DeCordova Room both have a long way to go. New concrete slab has been poured for Bosque Theatre.

 


Lower Level Progress

 

Kitchen Area


There has been a lot of progress made on the new kitchen areas. New walls now separate the various sections of the professional grade kitchen: ware room, freezer, cold storage, prep room, bakery, and so on. The kitchen will be located where the Convention Center offices once stood.

 

Lower Level Rooms

 

The new meeting rooms in the lower level continue to progress, along with Texas, Ranger, and Huaco. The wall facing Washington Avenue will eventually be demolished and a new wall will be constructed further out from the existing building's footprint.

 

 



Room Availability

 

Currently, the Brazos Ballroom and Cameron Room are available for rental. On June 1, 2010, Chisholm Hall is scheduled to become available again. On June 1, 2010, McLennan Hall comes back online.

 



 


Please call us at 800-321-9226 or 254-750-5810 to book your event.

Sincerely,

 

Waco CVB
PO Box 2570
Waco, Texas 76702-2570


Renovation Links


Photo Album: http://www.wacocvb.com/renovationpix.asp.


Renovation microsite: http://www.wacocvb.com/renovation-home.asp