One of the things I am worst at is waiting. But I'm so thankful that God brings things into my life where I must be totally dependent upon Him and learn to wait for His perfect timing. The most recent example of this is our current building project, and the addition of Phase 3. Much has actually been happening since last year when we began this adventure, and I'm eager to 'see the dirt flying' and watch the vision God has given Grace become a reality. It is appropriate to review some of the milestones God has led us through and events yet to come as we prepare for Pastor Joel to take us through a study of the book of Joshua.
Feb 2006 - Elders establish vision for ministry
Mar 2006 - Building, finance & campaign teams established
May 2006 - Vision communication at Annual Shepherding session
Aug 2006 - Brown, Brown & Associates, Inc., hired as
Phase 3 architects
Sep 2006 - Architect interviews with Ministry Leaders
Oct 2006 - 'For Such a Time as This' campaign kick-off
Nov 2006 - First Fruits offering received of $117,425
Nov 2006 - 3-year pledges received totaling $591,374
Jan 2007 - Phase 3 debt service level determined
Feb 2007 - Request for Proposal (RFP) sent to five contractors
Mar 2007 - Master Plan finalized, preliminary budget established
Mar 2007 - Mortgage financing recommended by Finance Committee
May 2007 - Frank Dale & Company selected as General Contractors
May 2007 - Special Use Permit (SUP) submitted to City of Lucas
Jun 2007 - SUP approved by Lucas Planning & Zoning Commission
Jul 2007 - SUP approved by Lucas City Council
Aug 2007 - Total pledge collection reaches $235,483
Aug 2007 - Design documents sent for initial bids
Here is where we believe God is taking us next:
Sep 2007 - Phase I & 2 fire alarm installation
Sep 2007 - Finalization of land donation, shared retention pond
Oct 2007 - Phase 3 financing finalization
Nov 2007 - Construction documents complete
Nov 2007 - Permitting process begins
Nov 2007 - Finalization of pricing contracts
Dec 2007 - Phase I & 2 sprinkler system installation
Dec 2007 - Permitting complete
Jan 2008 - Begin construction
Jul/Aug 2008 - Construction complete with certificate of occupancy
These dates can only be accomplished as God clears the way for us. And just as Joshua and the people of Israel entered God's promised land, it will take steps of faith for the community of Grace to move forward toward what God wants for us. The leadership at Grace is committed to seeing this new building become a reality. And as Pastor Joel reminded us this past Sunday, the reason for the building is to accomplish the ministry that God has in store for us. So as we watch the process unfold before us of putting up a building, may we rededicate ourselves to the mission of Grace: to reach our community for Christ and to help those who believe in Him, become more like Him. As we do this, God will handle all those details associated with putting up a structure that allows us to accomplish His will. To Him be the glory!