This decision applied the test of what constitutes a
"project" for purposes of CEQA established in the 2008
Save Tara v. City of
West Hollywood decision (45 Cal. 4th 116), which we wrote about in
our March 2009 DHA eAlert. (Follow
the
Archive link at the beginning of this message to read a summary of the Tara
case.)
In
Riverwatch, a
water district entered into an agreement with a landfill in San Diego County to
supply the landfill with water. The original EIR for the landfill project was
successfully challenged on the grounds that it did not adequately evaluate the
impacts of providing water to the landfill.
Although the County subsequently prepared a new EIR, the
water supply agreement was executed two years prior to the preparation of the new
EIR. The contract included a clause stipulating that the landfill
operator was responsible for any necessary CEQA review, but the Court of Appeal
concluded that the water district had thereby neglected its duty as a
responsible agency to retain discretionary review over the project.
The Court of Appeal further found that the water
agreement constituted a part of the landfill project. The water district failed
to comply with CEQA because it "approved" the project prior to conducting
environmental review. You can read the full decision at:
Riverwatch v. Olivehain
The County Board of Supervisors denied an application to
renew an existing use permit for operation of a private airport. The County
claimed the decision was exempt from CEQA under the statutory exemption established
by Public Resources Code Section 21080(b)(5), which applies to "projects which
a public agency rejects or disapproves." The California Supreme Court acknowledged that
disapproval of the project could lead to "environmental impacts associated with
alternative courses of action," but concluded that the statutory exemptions
under CEQA reflect legislative policy decisions that the court is bound to
follow.
California Native
Plant Society v. City Rancho Cordova
(March 24, 2009) 172 Cal. App. 4th 603
This Court of Appeals case is interesting because it highlights
a gray area of CEQA when it comes to designing adequate mitigation
measures. The CEQA Guidelines clearly prohibit deferring the formulation of
mitigation to a future date. However,
a mitigation measure may establish specific performance standards that must be
met that would mitigate the significant impact, and this may be achieved in
more than one specified way.
The Rancho Cordova
case trends in a different direction from some previous CEQA decisions, such as
the Citizens for a Better Environment v. City of Richmond case that was discussed
in the last DHA eAlert. Such
earlier decisions have invalidated mitigation measures that rely on future
formulation of mitigation plans, even when they establish performance
standards.
In the Rancho Cordova
case, the California Native Plant Society claimed that mitigation for
significant impacts to wetlands and vernal pool fairy shrimp habitat was
inadequate because the requirement for creation and protection of replacement
habitat did not identify a specific location for the replacement habitat. The Court rejected that argument, saying "the agency does not have to commit to any
particular mitigation measure in the EIR, as long as it commits to mitigating
the significant impacts of the project."
The Court ruled that the City could defer the development of the
specific manner in which off-site mitigation was provided.
While the decision affirmed the City's approach to
the mitigation, it also found that the City violated Planning and Zoning Law
because it failed to comply with a General Plan policy requiring the City to
"coordinate" with the U.S. Fish and Wildlife Service and the California
Department of Fish and Game when designing mitigation. The City had approved the
mitigation over the objections of these agencies. The Court found that "coordination" required more than "the mere solicitation and rejection of input"
from the agencies.
You can download the full decision
at:
CNPS v. Rancho Cordova
California Native
Plant Society v. City of Santa Cruz
(August 20, 2009) 177 Cal. App. 4th 957
This case centered on the alternatives selected for
evaluation in the EIR for a master plan for a 60-acre greenbelt owned by the
City of Santa Cruz. The plan included
a network of paved bicycle/pedestrian trails, one of which would potentially
cause a significant impact on the Santa Cruz tar plant.
The City evaluated four alternatives in the EIR, but
determined that all four alternatives were infeasible because they failed to
meet the objectives of the project and were undesirable from a policy
standpoint. The Court of
Appeal made several findings related to the adequacy of the alternatives:
- Alernatives do not need to be literally
impossible to be considered "infeasible." If an alternative conflicts with an
adopted local policy, that provides sufficient grounds for rejection.
-
Alternatives evaluated in an EIR need only be
potentially feasible. Actual feasibility may be determined at a later date.
-
The City did not error in omitting an off-site
alternative. The multi-use trail was just one component of the project, and
evaluation of an alternative to a project component is not required. Rather, an EIR is required to explore
alternatives to the project as a whole, which satisfy most of the primary
objectives of the project.
You can download the full decision
at:
CNPS v. Santa Cruz
California Native
Plant Society v. County of El Dorado (January 28, 2009) 170 Cal. App. 4th 1026
This was another case challenging the lead agency's approach
to mitigation. El Dorado County passed an ordinance in 1998 establishing a rare
plant impact fee program, and determined that the program was categorically
exempt from CEQA review. In 2006,
the County adopted a mitigated negative declaration for a congregate care
facility that would have significant impacts on special-status plants. The project sponsor was required to pay
a rare plant impact fee consistent with the County's fee program, in addition
to other requirements for mitigating the impacts.
The Court of Appeal ruled that a fee program must be
reviewed under CEQA, either programmatically or at the time of individual
project review, neither of which occurred. Among other rulings in the case, the Court also dismissed mitigation measures that had been added following the
close of public review. Because these measures were never circulated for
comment, the court wrote, they "cannot be relied upon to dispel the fair
argument of significant impacts."
You can read the full decision at:
CNPS v. County of El Dorado