
|
Further cost increases on the cards for Eskom's Medupi and Kusile power stations
|
To comment and respond to this article, and/or to any of the views and positions expressed, visit EE Publishers' blog: "The best from EE Publishers...", click on the title of the article of interest, and respond.
Note to media: This article may be used and published by interested media in whole or in part, as required, provided that the source is acknowledged.
Informed sources within Eskom Generation have indicated to EE Publishers that significant further cost increases can be expected for both Medupi and Kusile power stations... (more)
In the case of Medupi, provision has been made at a cost of "several hundred million rands" in the current R125-billion price tag to ensure that the plant is ready for the incorporation of flue-gas desulphurisation (FGD) plant. The FGD plant itsself will be installed under a seperate contract at the first general overhaul cycle of Medupi power station in about 2018.
Kusile, on the other hand, will have FGD plant installed from the beginning during the construction of the power station, and its cost is therefore included in the current overall R142-billion price tag. Further pushing up Kusile's price will be a significant additional cost of interest during construction, as well as contract price escallation, resulting from construction delays and the moratorium on placing of contracts since December 2008 due to the absence of a funding plan for the Eskom new-build programme.
Indications are that World Bank and other external finance for the construction of both Medupi and Kusile will be dependent on the incorporation of FGD technology in order to make the coal-fired power plants more environmentally acceptable. FGD plant will also increase the power plant operational costs due to significant additional requirements of both water and lime. These addition costs for Medupi and Kusile come at a time when Eskom is under severe pressure from government, political parties, industry, organised labour and electricity consumers in South Africa to reduce its multi-year price determination (MYPD) application to NERSA.
The current Eskom MYPD application asks for increases in the average price of electricity of 45% per annum for three consecutive years commencing April 2010, in order to fund the construction. This would cause the average electricity price to increase five-fold between 2008 and 2012 as follows:
Year: 2008 2009 2010 2011 2012 Increase: 1,27 x 1,31 x 1,45 x 1,45 x 1,45 = 5,08 x
The Eskom MYPD application has been met with shock within South Africa, and after initially indicating its support for the Eskom proposal, government has now requested alternative proposals and options from Eskom. Recent media reports have since indicated that Eskom is today submitting an alternative pricing application with reduced increases to NERSA for consideration.
It is understood that negotiations with the suppliers of FGD plant are underway at present for Kusile, and in the light of the commercial sensitivities before contracts are placed, Eskom is not at this stage prepared to indicate the expected cost of the FGD plant for either Kusile or Medupi.
However, it is common knowledge that the current price of Medupi excluding FGD and interest during construction is R90-billion, with a total price excluding FGD but including interst during construction of R125-billion, giving interest during construction of some R35-billion, or 28% of the total price excluding FGD. Kusile on the other hand is coming in at at total price of R142-billion including FGD, and analysts indicate that this is unlikely to be much different for Medupi.
Based on the current rate of exchange of US $1 = R7,5, the cost of R90-billion for a 4800 MW power plant translates to a cost of about US $2500 per kW of installed capacity, whille the "all in" cost of R142-billion translates to US $3944 per kW.
Generation plant - total plant cost USA India Romania
Gas turbine combined cycle plant, 140 MW $1411 $1170 $1140 Gas turbine simple cycle plant, 580 MW $860 $720 $710 Coal-fired steam plant (sub), 300 MW $2730 $1690 $2920 Coal-fired steam plant (sub), 500 MW $2290 $1440 $2530 Coal-fired steam plant (super), 800 MW $1960 $1290 $2250 Wind farm, 1 MW x 100 = 100 MW $1630 $1760 $1660 PV solar array, ground mounted, $/kW (AC) $8930 $7840 $8200
Source: World Bank, Energy Sector Management Assistance Program (ESMAP) report, August 2008
It should be noted that the above are "pre-global financial crisis" costs, in what analysts consider to be something of a sellers' market, and that, if anything, costs for power plant may since have reduced somewhat.
These benchmarks, however, exclude costs such as connection to the grid, pipelines and access roads outside the plant fence, raw water acquisition, project financing, customs or import duties, and land costs, and therefore some care should be excercised when making direct comparisons with Medupi and Kusile. Nevertheless, the ESMAP Report indicates that the prices for Medupi and Kusile are coming in at a significant premium over Indian and Chinese power plant, and even at a premium over American and European power plant. Yet the conventional wisdom is that the massive Eskom Medupi and Kusile power stations would bring South African customers significant cost savings due to economies of scale.
The answer to this apparent contradiction may lie in the onerous requirements for local content in the construction of South African built power stations, as well as the long construction times associated with these massive power plant projects, which brings a corresponding high cost of interest during construction.
These massive Eskom power plant projects may indeed have moved beyond the optimum size for "least cost" into the area of "diseconomies of scale", while at the same time significantly increasing the risks associated with having a single owner/developer/project manager, both in terms of cost and delivery time overruns, as well in the provision of the necessary funding.
In contrast, several smaller power plants, with shorter lead times, and constructed in parallel, may bring significant advantages in terms of cost, risk and diversity.
To comment and respond to this article, and/or to any of the views and positions expressed, visit EE Publishers' blog: "The best from EE Publishers...", click on the title of the article of interest, and respond. |
Eskom price application: Open workshop, panel discussion and debate hosted by Solidarity |
You are cordially invited to attend an open and interactive workshop, panel discussion and debate hosted by trade union, Solidarity. A panel of experts will discuss funding plans for Eskom and its MYPD (multi-year price determination) application to NERSA for an increase in the average price of electricity of 45% per annum for three consecutive years commencing April 2010.
DATE: 3 December 2009 TIME: 09h30 for 10h00 to 13h00, followed by lunch, courtesy of Solidarity VENUE: Centurion Lake Hotel, Centurion, Pretoria (directions below) COST: No cost, free-of-charge REGISTRATION: Click here to register online PANEL MEMBERS
Chris Yelland, managing director of EE Publishers, will act as the facilitator and chairperson for the discussion. The panel of experts will comprise:
- Brian Dames: Acting CEO of Eskom and COO of Eskom Generation, the company's largest division
- Chris Hart: Senior economist at Investment Solutions, a provider of multi-manager investment portfolios, with assets under management of over R100-billion
- Andrew Kenny: Consulting engineer, with degrees in physics and mechanical engineering, formerly of Eskom and senior research officer at the Energy Research Institute of the University of Cape Town
- Mike Schüssler: Senior economist and partner of Economists.co.za, a specialist economics consultancy to government, business and industry
BACKGROUND
The public hearings arranged by the National Energy Regulator of South Africa (NERSA) in February 2009 covered Eskom's application for an interim price increase in 2009. Former Eskom CEO Jacob Maroga indicated the interim application would cover primary energy and other operational cost increases. He called for an open discourse involving government, Eskom municipalities, industry, labour and other stakeholders, including the general public, to engage to develop a plan for the funding of Eskom's new-build programme.
Then, at the recent announcement of Eskom's MYPD application to NERSA for an increase in the average electricity price of 45% per annum per annum for three years to fund the new-build programme, Maroga indicated that the application was the start of the discourse into the funding plan that would culminate when NERSA announced its final determination in March 2010. He again called for open and broad-based engagement between Eskom and all stakeholders on the matter, indicating that the funding plan was not just an Eskom matter, but a matter for the whole country.
The Eskom pricing application would have the electricity price increase five-fold between 2008 and 2012.
This initiative by Solidarity, is part of its efforts to engage constructively and openly with its members and other stakeholders in the public interest in order to formulate a coherent and rational response to the Eskom MYPD application for presentation to NERSA.
REGISTRATION AND QUERIES
For catering and seating purposes, registration is essential. Please click here to register online Alternatively, please register as soon as possible by contacting Antoinette Koster, Solidarity, Email: akoster@solidariteit.co.za, Tel: 012 644-4329, indicating the names, cell phone numbers and email addresses of persons interested in attending. Your booking will be confirmed thereafter.
To avoid disappointment, please book early as seating is limited.
| |
|
|
(Flash "flip-page" edition)
(Flash flip-page edition)
|
Published by |
EE Publishers
P O Box 458
Muldersdrift
1747
South Africa
Tel 0115437000
Fax 0115437025
| |
|