WILMER VOLUNTEER FIRE DEPARTMENT GETS ASSISTANCE
The Wilmer Volunteer Fire and Rescue Department recently received $20,000 in funding from County Commission District 2 for assistance with the purchase of a used engine/pumper truck. The purchase, according to Deputy Chief and Board President Bill Donovan, will replace their back-up 1968 engine/pumper truck that is unreliable and will not hold water while not in use. The main engine/pumper truck is currently awaiting mechanical repairs, and the newly purchased back-up pumper will allow the main engine to be out of service for the necessary repair work.
DISTRICT 2 ROAD
PROJECTS UPDATE
District 2 road projects are moving along toward completion. A summary follows:
*John Shinn Road- Mobile County Project Number MCR-2004-205
Currently under construction. 99.9% complete.
*Cody Road- Mobile County Project Number MCR-2006-010
90% complete.
*Jeffrey Road and Wiggins Lane- Mobile County Project Number MCR-2008-203
Began work in January. 60% complete.
*Mack Hinton Road- Mobile County Project Number MCR-2008-204
Project is in design and bidding is anticipated to begin in early spring, 2011.
*Ziegler Blvd- City of Mobile and ALDOT Project
Forest Hill to Athey Drive 60% of design completed. Schillingers Road to Cody Road 40% of design completed.
*Old Shell Road- Mobile County and ALDOT Project
Anticipating completion in late April. 95% complete.
Update: County funded road projects in the City of Mobile
Road projects in the city limits of Mobile, paid for through the Mobile County Pay-As-You-Go Program, are tentatively scheduled to start construction as early as May, according to Nick Amberger, City of Mobile Engineer.
Click Here to view a complete list of the streets within the city limits of Mobile that are included in the PAYGO program using Mobile County PAYGO funding.
COUNTY FINANCES AT A GLANCE
According to Michelle Herman, Mobile County Finance Director, the 12/21/2010 budget report reflects revenue and expenditures for the first quarter of fiscal 2011. Through December we collected 23.83% of budgeted revenue. During the first quarter we expended 20.12 % of general fund budgeted expenditures. Click the link below to view a budget report showing expenditures through January 2011.
General Fund Budget Report
ALDOT OFFICIALS VISIT MOBILE TO HEAR TOP INFRASTRUCTURE PRIORITIES
The newly appointed Director of the Alabama Department of Transportation (ALDOT), John R. Cooper, along with the ALDOT Chief Engineer Don Vaughn, and ALDOT Division 9 Engineer Vince Calmetti, met with County Commissioners and County Engineers last week to discuss short- and long-term county road improvement projects.
The discussion included a review of a 2008 agreement in which ALDOT pledged to reimburse the County for $34 million in road projects in exchange for the county's support of ThyssenKrupp incentives of the same amount.
County engineers also requested assistance from ALDOT with the long-range plan to construct a western corridor from Bayou La Batre through West Mobile providing improved access to I-10, the Mobile Regional Airport and U.S. Highway 98. The project would include widening and improving existing roads and the construction of two new segments of connecting roadway.
Division 9 Engineer Vince Calmetti gave an update on the status of the proposed Mobile River Bridge. Currently, documents are being finalized for submission to the Federal Highway Administration (FHWA) for a modified route across the Mobile River. A public hearing will be scheduled toward the end of 2011. To get more information about attending this public hearing Click Here. Information will be posted at this site as it becomes available.
The last phase of the Highway 98 improvement project is underway. The connector for the roadway is being designed; the next steps include environmental surveying, review by the FHWA, and the purchase of right-of-way. ALDOT expects to begin construction of the connector in early 2012 with a completion date of late 2013 for all phases, which include:
* Big Creek Lake Bridge extension will begin in the spring of 2011.
* The Glenwood Overpass and the Connector (which will connect Schillinger to the end of the Big Creek Lake Bridge) phases are expected to begin in late 2011.
* The final phase is a base and pave project that is expected to be completed in late 2012.
SEMMES INCORPORATION EFFORT STATUS
Great progress has been made in reaching the goal of incorporating Semmes as the newest municipality in Mobile County. A group of individuals were sworn in by Mobile County Probate Judge Don Davis to serve as enumerators for collecting census data in Semmes, as required by Alabama law. This has been a door-to-door effort to collect the information required. The census is virtually complete and the information will be submitted to the Probate Judge. Upon submission to the Judge, he will have three days in which to issue the formal Order of Incorporation which will legally form the new city of Semmes. Helen Joyce, a member of the Committee to Incorporate Semmes, anticipates that this will be accomplished near the end of April. At that time, the Probate Judge will proceed with arranging for local municipal elections.
AUSTAL USA JOB OPPORTUNITIES
Austal USA, the shipbuilding facility located on the east side of the Mobile River is currently aggressively seeking to employ new apprentices for aluminum fabrication and welding, marine carpentry and cabinet-making, engineering, and electrical mechanics. Apprentices receive uniforms, safety equipment, power tools, and classroom instruction as well as on-the-job training. The U.S. Department of Defense recently awarded Austal USA a $4 billion contract to build 10 additional Littoral Combat Ships.
The company is currently ramping up its workforce to add approximately 1,800 more jobs. For more information regarding employment opportunities at Austal contact the Austal Human Resources Department at hr@austal.com or Click Here to view a current list of available jobs.